Trehawke Barton (Doddycross) Solar Farm (10.6 MW)

Trehawke Barton (Doddycross) Solar Farm is a 10.6 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2014; the record was last updated on 4 September 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10.6 MWsolar farm
operationalstatus in REPD
4 September 2018record last updated
Cornwallcouncil area

Planning timeline

DateStage
23 November 2012Application submitted
21 June 2013Planning permission granted
31 March 2014Operational

Project details

Technology
solar farm
Capacity
10.6 MW
Status (REPD)
operational
Record last updated
4 September 2018
Operator or applicant
Foresight
Planning authority
Cornwall
Planning application reference
PA12/11024
Site area
21.2 ha
Address (REPD)
Trehawke Barton Blunts Liskeard Cornwall
Council area (by location)
Cornwall
Time to decision
30 weeks
REPD reference
2121

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Trequite Farm solar parksolar farm9.9operational1.4
Land At Lanthronesolar farm5refused3.5
Wilton Farm (pv)solar farm9.5operational3.8
Land At Bake Farmsolar farm5operational4.1
Ford Farm Solar Farmsolar farm5operational4.9
Pensipple Farmsolar farm5operational6.1
Newton Ferrers solar parksolar farm19.5operational6.1
Dunstan Lodge solar farmsolar farm8.5refused7.6
Callington Solar Farmsolar farm6.4operational8.8