Energy Projects Near You

Solar, wind and battery projects near Saltash (PL12)

35 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PL12 (Cornwall): 1 is waiting for a planning decision, 17 approved but not yet running, 13 operational. The largest live scheme is West Kingsmill, Landulph (80 MW battery storage, approved on 18 July 2025, not yet built), 2.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

35projects within 10 km
1awaiting a decision
17approved, not running
13operational

Projects within 10 km of PL12

Projects of 1 MW and more (23)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Landulph Substation, Landulphbattery storagebattery storage99.9application withdrawnupdated Jul 2024Jan 2024—Jul 2024Cornwall2.5
West Kingsmill, Landulphbattery storagebattery storage80approved, not builtupdated Aug 2025Dec 2024granted Jul 2025Aug 2025Cornwall2.5
West Kingsmill Farm Solar Parksolar farmsolar farm1.6operationalupdated Oct 2014Feb 2011granted May 2011Oct 2014Cornwall2.5
Landulph, Ellbridge Lanebattery storagebattery storage49.9approved, not built may be out of dateupdated Feb 2023Nov 2022granted Feb 2023Feb 2023Cornwall3.1
Landulph Substation, Ellbridge Lanebattery storagebattery storage49.9approved, not builtupdated Sep 2023Mar 2023granted Sep 2023Sep 2023Cornwall3.1
Howton Farmsolar farmsolar farm4.4operationalupdated Jul 2011Jan 2011granted Apr 2011Jul 2011Cornwall3.4
North Wayton Farmsolar farmsolar farm5operationalupdated Sep 2015Oct 2012granted Apr 2013Sep 2015Cornwall3.4
Ernesettle Solar Farmsolar farmsolar farm4.1operationalupdated May 2016Jul 2015granted Sep 2015May 2016Plymouth4.9
Trevol Business Parkbattery storagebattery storage10approved, not built may be out of dateupdated Jan 2020Apr 2019granted Sep 2019Jan 2020Cornwall5.1
Land At Lanthronesolar farmsolar farm5refusedupdated Apr 2013Jun 2012refused Jan 2013Apr 2013Cornwall6.0
Warleigh Barton Solar Farmsolar farmsolar farm5operationalupdated Apr 2013Jun 2011granted Nov 2012Apr 2013Plymouth6.5
Dunstan Lodge solar farmsolar farmsolar farm8.5refusedupdated Nov 2013May 2013refused Aug 2013Nov 2013Cornwall6.7
Mendennick Wind Farmwind farmwind farm2.6application withdrawnupdated May 2013Jan 2013—May 2013Cornwall7.2
Mendennick Farmsolar farmsolar farm2.8operationalupdated Jul 2017Nov 2014granted Feb 2015Jul 2017Cornwall7.2
Newton Ferrers solar parksolar farmsolar farm19.5operationalupdated Apr 2016May 2014granted Aug 2014Apr 2016Cornwall7.7
Anthony Estate Solar Farmsolar farmsolar farm4.7operationalupdated Oct 2015Jul 2014granted Dec 2014Oct 2015Cornwall7.7
Land At Bake Farmsolar farmsolar farm5operationalupdated Jun 2016Jun 2015granted Sep 2015Jun 2016Cornwall7.8
Southdown Quarrysolar farmsolar farm1.5operationalupdated Dec 2015Jul 2014granted Oct 2014Dec 2015Cornwall7.8
Trequite Farm solar parksolar farmsolar farm9.9operationalupdated Oct 2014May 2013granted Aug 2013Oct 2014Cornwall8.2
Roborough Solar Farmsolar farmsolar farm2.6approved, not built may be out of dateupdated Mar 2023Nov 2022granted Mar 2023Mar 2023Plymouth9.3
Trehawke Barton (Doddycross) Solar Farmsolar farmsolar farm10.6operationalupdated Sep 2018Nov 2012granted Jun 2013Sep 2018Cornwall9.3
Roborough Solar Farmsolar farmsolar farm2.6approved, not built may be out of dateupdated Mar 2023Nov 2022granted Mar 2023Mar 2023Plymouth9.3
Wilton Farm (pv)solar farmsolar farm9.5operationalupdated Jun 2015Jan 2013granted Jan 2014Jun 2015Cornwall9.3
Smaller schemes under 1 MW, mostly rooftop solar (12)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Battery Box - Birch House - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Jan 2024Nov 2023granted Jan 2024Jan 2024Cornwall0.9
Spinnaker International Spinnaker House, Long Acrerooftop solarrooftop solar0.2approved, not builtupdated Dec 2023Oct 2023granted Dec 2023Dec 2023Cornwall0.9
China Fleet Country Clubsolar farmsolar farm0.6approved, not builtupdated Feb 2025Oct 2024granted Dec 2024Feb 2025Cornwall1.7
China Fleet Country Club, Pill Lanesolar farmsolar farm0.6application submittedupdated Sep 2025Oct 2024—Sep 2025Cornwall2.5
Kawasaki Factory, Ernesettle Lanerooftop solarrooftop solar—approved, not builtupdated Jun 2023Apr 2023granted Jun 2023Jun 2023Plymouth4.2
Princess Yachts Limitedrooftop solarrooftop solar0.7under constructionupdated Aug 2021Jul 2021—Aug 2021Plymouth8.3
Notre Dame Roman Catholic School, Notre Dame Closerooftop solarrooftop solar0.2approved, not builtupdated Apr 2025Feb 2025granted Mar 2025Apr 2025Plymouth8.8
Seaton Court, William Prance Roadrooftop solarrooftop solar0.2approved, not builtupdated Dec 2022Oct 2022granted Nov 2022Dec 2022Plymouth8.8
Plymouth Marine Laboratory, Prospect Placerooftop solarrooftop solar0.1approved, not built may be out of dateupdated Mar 2023Jan 2023granted Mar 2023Mar 2023Plymouth9.4
Armada Way Solar panelsrooftop solarrooftop solar—approved, not built may be out of dateupdated Feb 2022Jan 2021granted Apr 2021Feb 2022Plymouth9.4
Council Houserooftop solarrooftop solar—approved, not built may be out of dateupdated Mar 2022Jan 2021granted Mar 2021Mar 2022Plymouth9.4
Derriford Hospital, Derriford Roadrooftop solarrooftop solar—approved, not builtupdated Nov 2025Aug 2025granted Sep 2025Nov 2025Plymouth9.7

Distance from the average position of the PL12 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm19131326.5
Rooftop solar909001.4
Wind farm100000
Battery storage60500190

MW in pipeline: pending, approved and under-construction capacity.

How Cornwall decides solar, wind and battery applications

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

All projects in Cornwall

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PL12, 7 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.