Solar, wind and battery projects near Torpoint (PL10)

23 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PL10 (Cornwall): 2 are waiting for a planning decision, 15 approved but not yet running, 4 operational. The largest live scheme is Plymouth Stor Generation (20 MW battery storage, approved on 26 March 2025, not yet built), 7.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

23projects within 10 km
2awaiting a decision
15approved, not running
4operational

Projects within 10 km of PL10

Projects of 1 MW and more (8)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Southdown Quarrysolar farmsolar farm1.5operationalupdated Dec 2015Jul 2014granted Oct 2014Dec 2015Cornwall1.4
Mendennick Farmsolar farmsolar farm2.8operationalupdated Jul 2017Nov 2014granted Feb 2015Jul 2017Cornwall2.3
Mendennick Wind Farmwind farmwind farm2.6application withdrawnupdated May 2013Jan 2013—May 2013Cornwall2.4
Anthony Estate Solar Farmsolar farmsolar farm4.7operationalupdated Oct 2015Jul 2014granted Dec 2014Oct 2015Cornwall2.8
Trevol Business Parkbattery storagebattery storage10approved, not built may be out of dateupdated Jan 2020Apr 2019granted Sep 2019Jan 2020Cornwall3.6
Plymouth Stor Generationbattery storagebattery storage20approved, not builtupdated Apr 2025Jan 2025granted Mar 2025Apr 2025Plymouth7.4
Ernesettle Solar Farmsolar farmsolar farm4.1operationalupdated May 2016Jul 2015granted Sep 2015May 2016Plymouth7.7
Chelson Meadow Solar Farmsolar farmsolar farm13approved, not built may be out of dateupdated Sep 2025Feb 2022granted Jun 2022Sep 2025Plymouth8.8
Smaller schemes under 1 MW, mostly rooftop solar (15)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Princess Yachts Limitedrooftop solarrooftop solar0.7under constructionupdated Aug 2021Jul 2021—Aug 2021Plymouth4.3
Plymouth Marine Laboratory, Prospect Placerooftop solarrooftop solar0.1approved, not built may be out of dateupdated Mar 2023Jan 2023granted Mar 2023Mar 2023Plymouth5.0
Armada Way Solar panelsrooftop solarrooftop solar—approved, not built may be out of dateupdated Feb 2022Jan 2021granted Apr 2021Feb 2022Plymouth5.6
Council Houserooftop solarrooftop solar—approved, not built may be out of dateupdated Mar 2022Jan 2021granted Mar 2021Mar 2022Plymouth5.6
Staddon Lane - Micro Energy Storage Facilitybattery storagebattery storage0.2application withdrawnupdated Mar 2024Jan 2024—Mar 2024Plymouth6.8
Interfish, Wallsend Industrial Estatesolar farmsolar farm0.2application submittedJun 2026——Plymouth6.9
Sugar Mill Industrial Estate, Billacombe Roadrooftop solarrooftop solar0.3approved, not builtupdated Oct 2024Aug 2024granted Oct 2024Oct 2024Plymouth7.9
Spinnaker International Spinnaker House, Long Acrerooftop solarrooftop solar0.2approved, not builtupdated Dec 2023Oct 2023granted Dec 2023Dec 2023Cornwall8.1
China Fleet Country Clubsolar farmsolar farm0.6approved, not builtupdated Feb 2025Oct 2024granted Dec 2024Feb 2025Cornwall8.1
China Fleet Country Club, Pill Lanesolar farmsolar farm0.6application submittedupdated Sep 2025Oct 2024—Sep 2025Cornwall8.2
Lipson Community College, Bernice Terracerooftop solarrooftop solar0.3approved, not builtupdated Dec 2025Oct 2025granted Dec 2025Dec 2025Plymouth8.2
Battery Box - Birch House - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Jan 2024Nov 2023granted Jan 2024Jan 2024Cornwall8.3
Morrisons supermarket - Roof mounted Solar Photovoltaicsrooftop solarrooftop solar0.7approved, not builtupdated Mar 2022Feb 2022granted May 2022Mar 2022Plymouth8.3
Kawasaki Factory, Ernesettle Lanerooftop solarrooftop solar—approved, not builtupdated Jun 2023Apr 2023granted Jun 2023Jun 2023Plymouth8.7
Seaton Court, William Prance Roadrooftop solarrooftop solar0.2approved, not builtupdated Dec 2022Oct 2022granted Nov 2022Dec 2022Plymouth9.6

Distance from the average position of the PL10 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm8224014.4
Rooftop solar10010002.5
Wind farm100000
Battery storage4030030.2

MW in pipeline: pending, approved and under-construction capacity.

How Cornwall decides solar, wind and battery applications

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

All projects in Cornwall

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PL10, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.