Trevol Business Park (10 MW battery storage)
Trevol Business Park is a 10 MW battery storage project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 2 September 2019, not yet built; the record was last updated on 23 January 2020. REPD also records that the planning permission expired on 2 September 2022, so the project may not go ahead in this form. Check the planning authority's register for the latest position.
REPD also records that the planning permission expired on 2 September 2022, so the project may not go ahead in this form.
Planning timeline
| Date | Stage |
|---|---|
| 12 April 2019 | Application submitted |
| 2 September 2019 | Planning permission granted |
| 2 September 2022 | Permission expired |
Project details
- Technology
- battery storage (stand-alone storage)
- Capacity
- 10 MW
- Status (REPD)
- approved, not built
- Record last updated
- 23 January 2020
- Operator or applicant
- Londonwide Properties
- Planning authority
- Cornwall
- Planning application reference
- PA19/03228
- Address (REPD)
- Land At, Trevol Business Park, Torpoint, Cornwall
- Council area (by location)
- Cornwall
- Time to decision
- 20 weeks
- REPD reference
- 7404
Who decides
| Applications | Cornwall | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 225 | 10,236 |
| Refused | 49 (22%) | 19% |
| Solar refused | 31 of 159 | 12% |
| Onshore wind refused | 15 of 39 | 45% |
| Battery storage refused | 3 of 27 | 16% |
| Median time from submission to decision | 16.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 23 / 20 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Landulph Substation, Landulph | battery storage | 99.9 | application withdrawn | 7.3 |
| West Kingsmill, Landulph | battery storage | 80 | approved, not built | 7.3 |
| North Wayton Farm | solar farm | 5 | operational | 7.3 |
| Warleigh Barton Solar Farm | solar farm | 5 | operational | 7.9 |
| Landulph Substation, Ellbridge Lane | battery storage | 49.9 | approved, not built | 8.0 |
| Landulph, Ellbridge Lane | battery storage | 49.9 | approved, not built | 8.1 |
| Plymouth Stor Generation | battery storage | 20 | approved, not built | 8.1 |
| Chelson Meadow Solar Farm | solar farm | 13 | approved, not built | 9.0 |
| Land At Lanthrone | solar farm | 5 | refused | 9.2 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.3763, -4.2265).