West Kingsmill, Landulph (80 MW battery storage)

West Kingsmill, Landulph is an 80 MW battery storage project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 18 July 2025, not yet built; the record was last updated on 5 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

80 MWbattery storage
approved, not builtstatus in REPD
5 August 2025record last updated
Cornwallcouncil area

Planning timeline

DateStage
20 December 2024Application submitted
18 July 2025Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
80 MW
Status (REPD)
approved, not built
Record last updated
5 August 2025
Operator or applicant
Boultbee Brooks Real Estate Hereford Limited
Planning authority
Cornwall
Planning application reference
PA24/09330
Address (REPD)
West Kingsmill Landulph
Council area (by location)
Cornwall
Time to decision
30 weeks
Name in REPD
West Kingsmill, Landulph - Battery Storage
REPD reference
13687

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Landulph Substation, Landulphbattery storage99.9application withdrawn<0.1
Landulph Substation, Ellbridge Lanebattery storage49.9approved, not built0.7
Landulph, Ellbridge Lanebattery storage49.9approved, not built0.9
North Wayton Farmsolar farm5operational1.7
Dunstan Lodge solar farmsolar farm8.5refused5.0
Warleigh Barton Solar Farmsolar farm5operational5.7
Newton Ferrers solar parksolar farm19.5operational6.5
Land At Lanthronesolar farm5refused7.0
Trevol Business Parkbattery storage10approved, not built7.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.441, -4.2413).