Energy Projects Near You

Dunstan Lodge solar farm (8.5 MW)

Dunstan Lodge solar farm is an 8.5 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 29 August 2013; the record was last updated on 19 November 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.5 MWsolar farm
refusedstatus in REPD
19 November 2013record last updated
Cornwallcouncil area

Planning timeline

DateStage
20 May 2013Application submitted
29 August 2013Refused by the planning authority

Project details

Technology
solar farm
Capacity
8.5 MW
Status (REPD)
refused
Record last updated
19 November 2013
Operator or applicant
Bond Holdings Ltd
Planning authority
Cornwall
Planning application reference
PA13/03583
Address (REPD)
Land At Dunstan Lodge St Mellion Cornwall
Council area (by location)
Cornwall
Time to decision
14 weeks
REPD reference
1194

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Newton Ferrers solar parksolar farm19.5operational1.9
Landulph, Ellbridge Lanebattery storage49.9approved, not built4.1
Callington Solar Farmsolar farm6.4operational4.5
Landulph Substation, Ellbridge Lanebattery storage49.9approved, not built4.5
West Kingsmill, Landulphbattery storage80approved, not built5.0
Landulph Substation, Landulphbattery storage99.9application withdrawn5.0
North Wayton Farmsolar farm5operational6.3
Ford Farm Solar Farmsolar farm5operational6.3
Land At Lanthronesolar farm5refused6.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.474, -4.2898).