North Wayton Farm (5 MW solar farm)
North Wayton Farm is a 5 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2014; the record was last updated on 30 September 2015.
5 MWsolar farm
operationalstatus in REPD
30 September 2015record last updated
Cornwallcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 9 October 2012 | Application submitted |
| 9 April 2013 | Planning permission granted |
| 31 March 2014 | Operational |
Project details
- Technology
- solar farm
- Capacity
- 5 MW
- Status (REPD)
- operational
- Record last updated
- 30 September 2015
- Operator or applicant
- KS SPV21 Ltd
- Planning authority
- Cornwall
- Planning application reference
- PA12/09275
- Address (REPD)
- Landulph Saltash Cornwall
- Council area (by location)
- Cornwall
- Time to decision
- 26 weeks
- REPD reference
- 1776
Who decides
| Applications | Cornwall | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 225 | 10,236 |
| Refused | 49 (22%) | 19% |
| Solar refused | 31 of 159 | 12% |
| Onshore wind refused | 15 of 39 | 45% |
| Battery storage refused | 3 of 27 | 16% |
| Median time from submission to decision | 16.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 23 / 20 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| West Kingsmill, Landulph | battery storage | 80 | approved, not built | 1.7 |
| Landulph Substation, Landulph | battery storage | 99.9 | application withdrawn | 1.7 |
| Landulph Substation, Ellbridge Lane | battery storage | 49.9 | approved, not built | 1.9 |
| Landulph, Ellbridge Lane | battery storage | 49.9 | approved, not built | 2.4 |
| Warleigh Barton Solar Farm | solar farm | 5 | operational | 4.0 |
| Dunstan Lodge solar farm | solar farm | 8.5 | refused | 6.3 |
| Trevol Business Park | battery storage | 10 | approved, not built | 7.3 |
| Newton Ferrers solar park | solar farm | 19.5 | operational | 7.9 |
| Land At Lanthrone | solar farm | 5 | refused | 8.6 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.442, -4.217).