Landulph Substation, Landulph (99.9 MW battery storage)

Landulph Substation, Landulph is a 99.9 MW battery storage project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 25 June 2024; the record was last updated on 22 July 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

99.9 MWbattery storage
application withdrawnstatus in REPD
22 July 2024record last updated
Cornwallcouncil area

Planning timeline

DateStage
10 January 2024Application submitted
25 June 2024Application withdrawn

Project details

Technology
battery storage (stand-alone storage)
Capacity
99.9 MW
Status (REPD)
application withdrawn
Record last updated
22 July 2024
Operator or applicant
NZED Projectco 2 Limited
Planning authority
Cornwall
Planning application reference
PA23/08832
Address (REPD)
South East Of Landulph Substation Landulph
Council area (by location)
Cornwall
Name in REPD
Landulph Substation, Landulph - Battery Storage
REPD reference
13852

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
West Kingsmill, Landulphbattery storage80approved, not built<0.1
Landulph Substation, Ellbridge Lanebattery storage49.9approved, not built0.7
Landulph, Ellbridge Lanebattery storage49.9approved, not built0.9
North Wayton Farmsolar farm5operational1.7
Dunstan Lodge solar farmsolar farm8.5refused5.0
Warleigh Barton Solar Farmsolar farm5operational5.7
Newton Ferrers solar parksolar farm19.5operational6.5
Land At Lanthronesolar farm5refused7.0
Trevol Business Parkbattery storage10approved, not built7.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.441, -4.2413).