Landulph Substation, Landulph (99.9 MW battery storage)
Landulph Substation, Landulph is a 99.9 MW battery storage project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 25 June 2024; the record was last updated on 22 July 2024.
99.9 MWbattery storage
application withdrawnstatus in REPD
22 July 2024record last updated
Cornwallcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 10 January 2024 | Application submitted |
| 25 June 2024 | Application withdrawn |
Project details
- Technology
- battery storage (stand-alone storage)
- Capacity
- 99.9 MW
- Status (REPD)
- application withdrawn
- Record last updated
- 22 July 2024
- Operator or applicant
- NZED Projectco 2 Limited
- Planning authority
- Cornwall
- Planning application reference
- PA23/08832
- Address (REPD)
- South East Of Landulph Substation Landulph
- Council area (by location)
- Cornwall
- Name in REPD
- Landulph Substation, Landulph - Battery Storage
- REPD reference
- 13852
Who decides
| Applications | Cornwall | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 225 | 10,236 |
| Refused | 49 (22%) | 19% |
| Solar refused | 31 of 159 | 12% |
| Onshore wind refused | 15 of 39 | 45% |
| Battery storage refused | 3 of 27 | 16% |
| Median time from submission to decision | 16.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 23 / 20 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| West Kingsmill, Landulph | battery storage | 80 | approved, not built | <0.1 |
| Landulph Substation, Ellbridge Lane | battery storage | 49.9 | approved, not built | 0.7 |
| Landulph, Ellbridge Lane | battery storage | 49.9 | approved, not built | 0.9 |
| North Wayton Farm | solar farm | 5 | operational | 1.7 |
| Dunstan Lodge solar farm | solar farm | 8.5 | refused | 5.0 |
| Warleigh Barton Solar Farm | solar farm | 5 | operational | 5.7 |
| Newton Ferrers solar park | solar farm | 19.5 | operational | 6.5 |
| Land At Lanthrone | solar farm | 5 | refused | 7.0 |
| Trevol Business Park | battery storage | 10 | approved, not built | 7.3 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.441, -4.2413).