Energy Projects Near You

Landulph, Ellbridge Lane (49.9 MW battery storage)

Landulph, Ellbridge Lane is a 49.9 MW battery storage project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 6 February 2023, not yet built; the record was last updated on 22 February 2023. REPD also records that the planning permission expired on 6 February 2026, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtmay be out of datestatus in REPD
22 February 2023record last updated
Cornwallcouncil area

REPD also records that the planning permission expired on 6 February 2026, so the project may not go ahead in this form.

Planning timeline

DateStage
8 November 2022Application submitted
6 February 2023Planning permission granted
6 February 2026Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
22 February 2023
Operator or applicant
Pivoted Power Llp
Planning authority
Cornwall
Planning application reference
PA22/10000
Address (REPD)
Adjacent To Landulph National Grid 400kV Substation Ellbridge Lane Ellbridge
Council area (by location)
Cornwall
Time to decision
13 weeks
Name in REPD
Landulph, Ellbridge Lane - Battery Storage Facility
REPD reference
12697

Earlier applications for this site

ApplicationMWSubmittedOutcome
Ellbridge Lane PA19/0393549.93 June 2019replaced by a revised application

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Landulph Substation, Ellbridge Lanebattery storage49.9approved, not built0.5
Landulph Substation, Landulphbattery storage99.9application withdrawn0.9
West Kingsmill, Landulphbattery storage80approved, not built0.9
North Wayton Farmsolar farm5operational2.4
Dunstan Lodge solar farmsolar farm8.5refused4.1
Newton Ferrers solar parksolar farm19.5operational5.6
Warleigh Barton Solar Farmsolar farm5operational6.4
Land At Lanthronesolar farm5refused6.7
Trevol Business Parkbattery storage10approved, not built8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.4473, -4.2497).