Warleigh Barton Solar Farm (5 MW)

Warleigh Barton Solar Farm is a 5 MW solar farm project in Plymouth, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 20 March 2013; the record was last updated on 11 April 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
11 April 2013record last updated
Plymouthcouncil area

Planning timeline

DateStage
1 June 2011Application submitted
2 November 2012Planning permission granted
20 March 2013Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
11 April 2013
Operator or applicant
Low Carbon Solar
Planning authority
South Hams
Planning application reference
04/0770/11/F
Address (REPD)
Station Road, Tamerton Foliot
Council area (by location)
Plymouth
Time to decision
74 weeks
REPD reference
1583

Who decides

ApplicationsSouth HamsUK
Decided applications (solar, wind, battery)3610,236
Refused6 (17%)19%
Solar refused3 of 2812%
Onshore wind refused3 of 345%
Battery storage refused0 of 516%
Median time from submission to decision13.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
North Wayton Farmsolar farm5operational4.0
West Kingsmill, Landulphbattery storage80approved, not built5.7
Landulph Substation, Landulphbattery storage99.9application withdrawn5.7
Landulph Substation, Ellbridge Lanebattery storage49.9approved, not built5.9
Landulph, Ellbridge Lanebattery storage49.9approved, not built6.4
Chelson Meadow Solar Farmsolar farm13approved, not built7.7
Trevol Business Parkbattery storage10approved, not built7.9
Plymouth Stor Generationbattery storage20approved, not built8.2
Newnham Estatesolar farm14operational9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.4344, -4.1618).