Newnham Estate (14 MW solar farm)

Newnham Estate is a 14 MW solar farm project in South Hams, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2015; the record was last updated on 2 April 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14 MWsolar farm
operationalstatus in REPD
2 April 2015record last updated
South Hamscouncil area

Planning timeline

DateStage
15 August 2014Application submitted
27 November 2014Planning permission granted
27 November 2014Appeal allowed
1 December 2014Construction started
31 March 2015Operational

Project details

Technology
solar farm
Capacity
14 MW
Status (REPD)
operational
Record last updated
2 April 2015
Operator or applicant
Solstice Renewables
Planning authority
South Hams
Planning application reference
49/2133/14/F
Site area
33.6 ha
Address (REPD)
SX559 587, Hemerdon, Plympton
Council area (by location)
South Hams
Time to decision
15 weeks
REPD reference
2225

Who decides

ApplicationsSouth HamsUK
Decided applications (solar, wind, battery)3610,236
Refused6 (17%)19%
Solar refused3 of 2812%
Onshore wind refused3 of 345%
Battery storage refused0 of 516%
Median time from submission to decision13.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Langage Solar Farmsolar farm5operational2.6
Lee Moor China Clay Workssolar farm9.5operational4.5
Chelson Meadow Solar Farmsolar farm13approved, not built6.0
Balls Wood Solar Farmsolar farm8.7operational6.5
Plymouth Stor Generationbattery storage20approved, not built7.4
Newton Downs Farmsolar farm5operational9.1
Creacombe Solar Farmsolar farm7.3operational9.2
Warleigh Barton Solar Farmsolar farm5operational9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.4085, -4.0295).