Energy Projects Near You

Renewable energy projects in South Hams

43 solar, wind or battery projects of 150 kW or more are located in South Hams (REPD, July 2026 extract): 3 pending, 11 approved but not running, 17 operational and 5 refused. The council refused 6 of 36 decided applications (17%; UK 19%), with a median 13 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

43projects in the council area
3awaiting a decision
11approved, not running
17%of decisions refused

How South Hams decides

ApplicationsSouth HamsUK
Decided applications (solar, wind, battery)3610,236
Refused6 (17%)19%
Solar refused3 of 2812%
Onshore wind refused3 of 345%
Battery storage refused0 of 516%
Median time from submission to decision13.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Projects in South Hams

Projects of 1 MW and more (31)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Hood Barton, Stavertonbattery storagebattery storage99application submittedupdated Jan 2025Dec 2024—Jan 2025
Riverford Farmbattery storagebattery storage49.9permission expiredupdated Aug 2020Oct 2017granted Dec 2017Aug 2020
Newnham Estatesolar farmsolar farm14operationalupdated Apr 2015Aug 2014granted Nov 2014Apr 2015
Lee Moor China Clay Workssolar farmsolar farm9.5operationalupdated Oct 2016Aug 2014granted Oct 2014Oct 2016
Balls Wood Solar Farmsolar farmsolar farm8.7operationalupdated Mar 2016Jul 2014granted Oct 2014Mar 2016
Coombeshead Solar Farmsolar farmsolar farm8operationalupdated May 2018Jan 2014granted Aug 2014May 2018
Creacombe Solar Farmsolar farmsolar farm7.3operationalupdated Oct 2018Apr 2017granted Mar 2018Oct 2018
Parkview solar parksolar farmsolar farm6.5operationalupdated Aug 2015Jun 2014granted Oct 2014Aug 2015
Hazard Farmsolar farmsolar farm6.4operationalupdated Jun 2014Oct 2012granted May 2013Jun 2014
Marley Thatch Solar Farmsolar farmsolar farm6.3operationalupdated Apr 2013Mar 2012granted Jun 2012Apr 2013
Halwell Airfieldsolarsolar5.7refusedupdated Jan 2014Sep 2013refused Nov 2013Jan 2014
Hatchlands Farmsolar farmsolar farm5.2operationalupdated Mar 2013Aug 2012granted Oct 2012Mar 2013
Langage Solar Farmsolar farmsolar farm5operationalupdated Aug 2011Jan 2011granted Mar 2011Aug 2011
Bidwell Solar Farmsolar farmsolar farm5operationalupdated Jul 2015May 2013granted Jul 2013Jul 2015
Lower Blakemore Farmsolar farmsolar farm5refused on appealupdated Apr 2016Sep 2014refused Jun 2015Apr 2016
Newton Downs Farmsolar farmsolar farm5operationalupdated Mar 2018Jun 2015granted Jul 2016Mar 2018
Land at Oldstone Farmsolar farmsolar farm5operationalupdated Jun 2017Aug 2015granted Apr 2016Jun 2017
Beech Tree Farm Wind Turbineswind farmwind farm4.9application withdrawnupdated Aug 2005Oct 2004—Aug 2005
Place Barton Farmsolar farmsolar farm4.9operationalupdated Jun 2017Apr 2015granted Sep 2015Jun 2017
Totnes Community Wind Farmwind farmwind farm4.6refusedupdated Apr 2013Aug 2012refused Feb 2013Apr 2013
Lower Slade Farmsolar farmsolar farm4.1operationalupdated Dec 2015Feb 2013granted Aug 2014Dec 2015
Beech Tree Farmwind farmwind farm4refused on appealupdated Dec 2010Nov 2007refused Feb 2008Dec 2010
Blackawton Solar Farmsolar farmsolar farm3operationalupdated Dec 2014Dec 2013granted Mar 2014Dec 2014
Town Farm, Blackawtonbattery storagebattery storage3application withdrawnupdated May 2024Apr 2024—May 2024
Yealmptonsolarsolar2.6application withdrawnupdated Aug 2017Oct 2013—Aug 2017
Colleen Farmsolar farmsolar farm2.2abandonedupdated Oct 2016Jun 2014granted Mar 2015Oct 2016
Luson Farmsolar farmsolar farm1.9operationalupdated Mar 2013Nov 2012granted Jan 2013Mar 2013
Mayflower Water Treatment Works, Roborough Downsolar farmsolar farm1.6approved, not builtupdated Apr 2024Jul 2023granted Feb 2024Apr 2024
Stumpy Postwind turbinewind turbine1.3refusedupdated Aug 2005Mar 2003refused May 2003Aug 2005
Island Park Lodgewind farmwind farm1.3application withdrawnupdated Aug 2005Jan 2002—Aug 2005
Tamerton Road, Roboroughrooftop solarrooftop solar1approved, not builtupdated Mar 2022Feb 2022granted Apr 2022Mar 2022
Smaller schemes under 1 MW, mostly rooftop solar (12)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Langage Solar Parkbattery storagebattery storage0.5approved, not built may be out of dateupdated Apr 2025Jun 2019granted Oct 2019Apr 2025
Endsleigh Garden Centre, Endsleighrooftop solarrooftop solar0.3approved, not builtupdated Dec 2022Sep 2022granted Dec 2022Dec 2022
Western Wood Way, Plymptonrooftop solarrooftop solar0.2approved, not builtupdated Jun 2022May 2022granted Jul 2022Jun 2022
Bandvulc Remoulds, Gillard Way Solar Photovoltaics Systemsolar farmsolar farm0.2approved, not builtupdated Feb 2024Sep 2023granted Jan 2024Feb 2024
Butts Park, Newton Ferrers Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Jan 2025Jan 2025granted Apr 2025Jan 2025
Eastern Wood Road, Plympton - Batteriesbattery storagebattery storage0.2approved, not builtupdated May 2025Jan 2025granted Mar 2025May 2025
Tamerton Road, Woolwell - Micro Energy Storagebattery storagebattery storage0.2application submittedupdated May 2026Apr 2026—May 2026
Western Wood Way, Langage Business Parkrooftop solarrooftop solar0.1approved, not builtupdated Dec 2024Sep 2024granted Nov 2024Dec 2024
Start Point Lighthouse - Supply and Installation of Wind Turbinewind turbinewind turbine—no application requiredupdated Dec 2021——Dec 2021
Deep Lanebattery storagebattery storage—approved, not built may be out of dateupdated May 2022May 2022granted Aug 2022May 2022
Littlehempston Water Treatment Works, Littlehempstonsolar farmsolar farm—application submitted may be out of dateupdated Nov 2023Oct 2023—Nov 2023
Vacsaxrooftop solarrooftop solar—approved, not builtupdated May 2025Feb 2025granted Mar 2025May 2025

Postcode districts in South Hams

DistrictProjects within 10 kmPendingApprovedOperational
PL8361226
PL2118097
TQ610132
TQ76002
TQ86001
TQ923338
TQ1012126

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to South Hams by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.