Energy Projects Near You

Creacombe Solar Farm (7.3 MW)

Creacombe Solar Farm is a 7.3 MW solar farm project in South Hams, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 January 2020; the record was last updated on 24 October 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.3 MWsolar farm
operationalstatus in REPD
24 October 2018record last updated
South Hamscouncil area

Planning timeline

DateStage
24 April 2017Application submitted
14 March 2018Planning permission granted
5 September 2019Construction started
1 January 2020Operational

Project details

Technology
solar farm
Capacity
7.3 MW
Status (REPD)
operational
Record last updated
24 October 2018
Operator or applicant
Gnaton Farm
Planning authority
South Hams
Planning application reference
1109/17/FUL
Site area
10.9 ha
Address (REPD)
Creacombe Farm, Yealmpton, Plymouth, Devon
Council area (by location)
South Hams
Time to decision
46 weeks
REPD reference
6591

Who decides

ApplicationsSouth HamsUK
Decided applications (solar, wind, battery)3610,236
Refused6 (17%)19%
Solar refused3 of 2812%
Onshore wind refused3 of 345%
Battery storage refused0 of 516%
Median time from submission to decision13.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Newton Downs Farmsolar farm5operational3.9
Balls Wood Solar Farmsolar farm8.7operational4.7
Langage Solar Farmsolar farm5operational6.6
Newnham Estatesolar farm14operational9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.3332, -3.9763).