Newton Downs Farm (5 MW solar farm)

Newton Downs Farm is a 5 MW solar farm project in South Hams, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 February 2017; the record was last updated on 2 March 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
2 March 2018record last updated
South Hamscouncil area

Planning timeline

DateStage
26 June 2015Application submitted
15 July 2016Planning permission granted
31 October 2016Construction started
15 February 2017Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
2 March 2018
Operator or applicant
Core Aries (Renewable Energy)
Planning authority
South Hams
Planning application reference
37/1426/15/F
Site area
11.9 ha
Address (REPD)
Newton Downs Farm, Newton Ferrers, Plymouth, Devon
Council area (by location)
South Hams
Time to decision
55 weeks
REPD reference
5451

Who decides

ApplicationsSouth HamsUK
Decided applications (solar, wind, battery)3610,236
Refused6 (17%)19%
Solar refused3 of 2812%
Onshore wind refused3 of 345%
Battery storage refused0 of 516%
Median time from submission to decision13.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Balls Wood Solar Farmsolar farm8.7operational2.6
Creacombe Solar Farmsolar farm7.3operational3.9
Langage Solar Farmsolar farm5operational7.1
Plymouth Stor Generationbattery storage20approved, not built7.4
Chelson Meadow Solar Farmsolar farm13approved, not built7.5
Newnham Estatesolar farm14operational9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.3264, -4.0303).