Riverford Farm (49.9 MW battery storage)

Riverford Farm is a 49.9 MW battery storage project in South Hams, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 5 January 2021; the record was last updated on 21 August 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
permission expiredstatus in REPD
21 August 2020record last updated
South Hamscouncil area

Planning timeline

DateStage
18 October 2017Application submitted
4 December 2017Planning permission granted
5 January 2021Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
permission expired
Record last updated
21 August 2020
Operator or applicant
Abham Storage / Statera Energy
Planning authority
South Hams
Planning application reference
3360/17/FUL
Address (REPD)
Riverford Farm, Zc88 at A384 to Staverton Brid, Staverton, Totnes, Devon
Council area (by location)
South Hams
Time to decision
7 weeks
REPD reference
7078

Who decides

ApplicationsSouth HamsUK
Decided applications (solar, wind, battery)3610,236
Refused6 (17%)19%
Solar refused3 of 2812%
Onshore wind refused3 of 345%
Battery storage refused0 of 516%
Median time from submission to decision13.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hood Barton, Stavertonbattery storage99application submitted<0.1
Bidwell Solar Farmsolar farm5operational2.5
Lower Blakemore Farmsolar farm5refused on appeal4.3
Parkview solar parksolar farm6.5operational4.9
Hazard Farmsolar farm6.4operational5.1
Hatchlands Farmsolar farm5.2operational5.7
Waye Bartonsolar farm5application withdrawn6.2
Marley Thatch Solar Farmsolar farm6.3operational6.9
Rydon Farmsolar farm12operational8.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.4618, -3.7318).