Energy Projects Near You

Parkview solar park (6.5 MW)

Parkview solar park is a 6.5 MW solar farm project in South Hams, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2015; the record was last updated on 24 August 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.5 MWsolar farm
operationalstatus in REPD
24 August 2015record last updated
South Hamscouncil area

Planning timeline

DateStage
26 June 2014Application submitted
28 October 2014Planning permission granted
1 February 2015Construction started
31 March 2015Operational

Project details

Technology
solar farm
Capacity
6.5 MW
Status (REPD)
operational
Record last updated
24 August 2015
Operator or applicant
NextEnergy
Planning authority
South Hams
Planning application reference
50/1623/14/F
Site area
13.6 ha
Address (REPD)
Land at SX765, 687, east of Parkfield Farm, Ashburton
Council area (by location)
South Hams
Time to decision
18 weeks
REPD reference
1846

Who decides

ApplicationsSouth HamsUK
Decided applications (solar, wind, battery)3610,236
Refused6 (17%)19%
Solar refused3 of 2812%
Onshore wind refused3 of 345%
Battery storage refused0 of 516%
Median time from submission to decision13.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hood Barton, Stavertonbattery storage99application submitted4.9
Riverford Farmbattery storage49.9permission expired4.9
Bidwell Solar Farmsolar farm5operational7.4
Rydon Farmsolar farm12operational8.1
Waye Bartonsolar farm5application withdrawn8.6
Lower Blakemore Farmsolar farm5refused on appeal9.1
Hatchlands Farmsolar farm5.2operational9.4
Hazard Farmsolar farm6.4operational9.4
Marley Thatch Solar Farmsolar farm6.3operational9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.5047, -3.7497).