Energy Projects Near You

Solar, wind and battery projects near Buckfastleigh (TQ11)

11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TQ11 (Teignbridge): 2 are waiting for a planning decision, 1 approved but not yet running, 5 operational. The largest live scheme is Hood Barton, Staverton (99 MW battery storage, application submitted on 12 December 2024, no decision recorded), 4.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects within 10 km
2awaiting a decision
1approved, not running
5operational

Projects within 10 km of TQ11

Projects of 1 MW and more (9)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Parkview solar parksolar farmsolar farm6.5operationalupdated Aug 2015Jun 2014granted Oct 2014Aug 2015South Hams3.5
Hood Barton, Stavertonbattery storagebattery storage99application submittedupdated Jan 2025Dec 2024—Jan 2025South Hams4.4
Riverford Farmbattery storagebattery storage49.9permission expiredupdated Aug 2020Oct 2017granted Dec 2017Aug 2020South Hams4.4
Bidwell Solar Farmsolar farmsolar farm5operationalupdated Jul 2015May 2013granted Jul 2013Jul 2015South Hams6.1
Hatchlands Farmsolar farmsolar farm5.2operationalupdated Mar 2013Aug 2012granted Oct 2012Mar 2013South Hams6.5
Marley Thatch Solar Farmsolar farmsolar farm6.3operationalupdated Apr 2013Mar 2012granted Jun 2012Apr 2013South Hams6.6
Hazard Farmsolar farmsolar farm6.4operationalupdated Jun 2014Oct 2012granted May 2013Jun 2014South Hams7.1
Lower Blakemore Farmsolar farmsolar farm5refused on appealupdated Apr 2016Sep 2014refused Jun 2015Apr 2016South Hams7.5
Totnes Community Wind Farmwind farmwind farm4.6refusedupdated Apr 2013Aug 2012refused Feb 2013Apr 2013South Hams9.7
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Linhay Hill Quarry, Settling Pond Solar Panel Arraysolar farmsolar farm0.5approved, not builtupdated Oct 2024Jul 2024granted Sep 2024Oct 2024Teignbridge5.9
Littlehempston Water Treatment Works, Littlehempstonsolar farmsolar farm—application submitted may be out of dateupdated Nov 2023Oct 2023—Nov 2023South Hams8.4

Distance from the average position of the TQ11 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm811510.5
Wind farm100010
Battery storage2100099

MW in pipeline: pending, approved and under-construction capacity.

How Teignbridge decides solar, wind and battery applications

ApplicationsTeignbridgeUK
Decided applications (solar, wind, battery)1410,236
Refused5 (36%)19%
Solar refused4 of 1212%
Battery storage refused1 of 216%
Median time from submission to decision12.4 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

All projects in Teignbridge

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TQ11, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.