Energy Projects Near You

Solar, wind and battery projects near Newton Abbot (TQ13)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TQ13 (Teignbridge): 2 are waiting for a planning decision, 6 approved but not yet running. The largest live scheme is Apple Tree Close (5 MW solar farm, approved on 31 May 2016, not yet built; REPD status may be out of date), 5.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
2awaiting a decision
6approved, not running
0operational

Projects within 10 km of TQ13

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Apple Tree Closesolar farmsolar farm5approved, not built may be out of dateupdated May 2020Oct 2015granted May 2016May 2020Teignbridge5.3
Smaller schemes under 1 MW, mostly rooftop solar (7)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Northcombe Solar Farmsolar farmsolar farm—application submitted may be out of dateupdated Feb 2021Jan 2021—Feb 2021Teignbridge2.7
Newton Road, Bovey Tracey - Micro Energy Storage Facilitybattery storagebattery storage0.2application submitted may be out of dateupdated Jul 2024Jul 2024—Jul 2024Teignbridge3.4
Newton Road & Pottery Road, Bovey Tracey - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Jun 2026Mar 2026granted Apr 2026Jun 2026Teignbridge3.4
Paramount 21, Old Newton Roadrooftop solarrooftop solar0.4approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026Teignbridge4.5
Brooke House, Sabre Closerooftop solarrooftop solar0.3approved, not builtupdated Feb 2023Oct 2022granted Dec 2022Feb 2023Teignbridge4.5
Linhay Hill Quarry, Settling Pond Solar Panel Arraysolar farmsolar farm0.5approved, not builtupdated Oct 2024Jul 2024granted Sep 2024Oct 2024Teignbridge7.6
Sibelco UK Preston Manor Works, Kingsteigntonrooftop solarrooftop solar0.8approved, not builtupdated Mar 2025Jan 2025granted Jan 2025Mar 2025Teignbridge8.0

Distance from the average position of the TQ13 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm312005.5
Rooftop solar303001.5
Battery storage211000.4

MW in pipeline: pending, approved and under-construction capacity.

How Teignbridge decides solar, wind and battery applications

ApplicationsTeignbridgeUK
Decided applications (solar, wind, battery)1410,236
Refused5 (36%)19%
Solar refused4 of 1212%
Battery storage refused1 of 216%
Median time from submission to decision12.4 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

All projects in Teignbridge

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TQ13, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.