Energy Projects Near You

Solar, wind and battery projects near Dawlish (EX7)

12 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of EX7 (Teignbridge): 2 are waiting for a planning decision, 1 approved but not yet running, 4 operational. The largest live scheme is Devon Cliffs Holiday Centre, Sandy Bay (0.5 MW rooftop solar, approved on 24 March 2023, not yet built), 8.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12projects within 10 km
2awaiting a decision
1approved, not running
4operational

Projects within 10 km of EX7

Projects of 1 MW and more (6)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Sawmills Solar Farmsolar farmsolar farm6.5operationalupdated May 2018May 2014granted Nov 2014May 2018Teignbridge4.5
Higher Humber Farmsolar farmsolar farm5.9refused on appealupdated Feb 2017Jan 2015refused Apr 2016Feb 2017Teignbridge7.6
Liverton Farmsolar farmsolar farm4.8operationalupdated Mar 2015Oct 2013granted Jan 2014Mar 2015East Devon8.9
Bystock Solar Farmsolar farmsolar farm4.1operationalupdated May 2015Jul 2014granted Sep 2014May 2015East Devon9.3
Coombe Farmsolar farmsolar farm8operationalupdated Jun 2015May 2014granted Sep 2014Jun 2015East Devon9.8
Veiges Farm Solar Parksolar farmsolar farm5abandonedupdated Feb 2019Sep 2015granted Feb 2016Feb 2019East Devon9.9
Smaller schemes under 1 MW, mostly rooftop solar (6)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Old Teignmouth Road - Micro Energy Storage Facilitybattery storagebattery storage0.2application withdrawnupdated Sep 2024Jul 2024—Sep 2024Teignbridge1.5
Langdon Hospital, Langdonsolar farmsolar farm—application submittedupdated Dec 2025Nov 2025—Dec 2025Teignbridge1.7
Langdon Hospital, Langdonbattery storagebattery storage—application submittedupdated Dec 2025Nov 2025—Dec 2025Teignbridge1.7
Bradham Lane - Micro Energy Storagebattery storagebattery storage0.2application withdrawnupdated Apr 2026Jan 2026—Apr 2026East Devon7.1
Devon Cliffs Holiday Centre, Sandy Bayrooftop solarrooftop solar0.5approved, not builtupdated Mar 2023Feb 2023granted Mar 2023Mar 2023East Devon8.1
Lower Veiges Plantationbattery storagebattery storage—abandonedupdated Feb 2019Dec 2015—Feb 2019East Devon9.9

Distance from the average position of the EX7 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm710410
Rooftop solar101000.5
Battery storage410000

MW in pipeline: pending, approved and under-construction capacity.

How Teignbridge decides solar, wind and battery applications

ApplicationsTeignbridgeUK
Decided applications (solar, wind, battery)1410,236
Refused5 (36%)19%
Solar refused4 of 1212%
Battery storage refused1 of 216%
Median time from submission to decision12.4 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

All projects in Teignbridge

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.