Energy Projects Near You

Sawmills Solar Farm (6.5 MW)

Sawmills Solar Farm is a 6.5 MW solar farm project in Teignbridge, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 16 March 2015; the record was last updated on 2 May 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.5 MWsolar farm
operationalstatus in REPD
2 May 2018record last updated
Teignbridgecouncil area

Planning timeline

DateStage
30 May 2014Application submitted
7 November 2014Planning permission granted
4 February 2015Construction started
16 March 2015Operational

Project details

Technology
solar farm
Capacity
6.5 MW
Status (REPD)
operational
Record last updated
2 May 2018
Operator or applicant
Foresight
Planning authority
Teignbridge
Planning application reference
14/01576/MAJ
Site area
28.7 ha
Address (REPD)
Sawmills, Ashcombe Estate, Ashcombe, Devon
Council area (by location)
Teignbridge
Time to decision
23 weeks
REPD reference
2335

Who decides

ApplicationsTeignbridgeUK
Decided applications (solar, wind, battery)1410,236
Refused5 (36%)19%
Solar refused4 of 1212%
Battery storage refused1 of 216%
Median time from submission to decision12.4 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Higher Humber Farmsolar farm5.9refused on appeal4.3
Apple Tree Closesolar farm5approved, not built7.8
Court Barton Farm, Coffinswell Solar Farmsolar farm21approved, not built9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.5921, -3.5337).