Energy Projects Near You

Court Barton Farm, Coffinswell Solar Farm (21 MW)

Court Barton Farm, Coffinswell Solar Farm is a 21 MW solar farm project in Teignbridge, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 15 August 2023, not yet built; the record was last updated on 11 September 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

21 MWsolar farm
approved, not builtstatus in REPD
11 September 2023record last updated
Teignbridgecouncil area

Planning timeline

DateStage
8 August 2022Application submitted
15 August 2023Planning permission granted
15 August 2026Permission expired

Project details

Technology
solar farm
Capacity
21 MW
Status (REPD)
approved, not built
Record last updated
11 September 2023
Operator or applicant
Coubar Energy Limited (Windel)
Planning authority
Teignbridge
Planning application reference
22/01533/MAJ
Site area
25.4 ha
Address (REPD)
Court Barton Farm, Coffinswell
Council area (by location)
Teignbridge
Time to decision
53 weeks
Contracts for Difference
AR6
Name in REPD
Court Barton Farm, Coffinswell - Solar Farm
REPD reference
9530

Who decides

ApplicationsTeignbridgeUK
Decided applications (solar, wind, battery)1410,236
Refused5 (36%)19%
Solar refused4 of 1212%
Battery storage refused1 of 216%
Median time from submission to decision12.4 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Barton Hill Industrial Parkbattery storage22.5operational2.5
Rydon Farmsolar farm12operational5.0
Higher Humber Farmsolar farm5.9refused on appeal6.4
Waye Bartonsolar farm5application withdrawn7.2
Sawmills Solar Farmsolar farm6.5operational9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.5055, -3.5647).