Energy Projects Near You

Waye Barton (5 MW solar farm)

Waye Barton is a 5 MW solar farm project in Teignbridge, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 14 January 2016; the record was last updated on 6 October 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
application withdrawnstatus in REPD
6 October 2015record last updated
Teignbridgecouncil area

Planning timeline

DateStage
21 August 2015Application submitted
14 January 2016Application withdrawn

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
application withdrawn
Record last updated
6 October 2015
Operator or applicant
Lark Energy
Planning authority
Teignbridge
Planning application reference
15/02090/MAJ
Site area
14.4 ha
Address (REPD)
Land At Waye Barton, Littlehempston, Totnes
Council area (by location)
Teignbridge
REPD reference
5358

Who decides

ApplicationsTeignbridgeUK
Decided applications (solar, wind, battery)1410,236
Refused5 (36%)19%
Solar refused4 of 1212%
Battery storage refused1 of 216%
Median time from submission to decision12.4 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Rydon Farmsolar farm12operational4.6
Riverford Farmbattery storage49.9permission expired6.2
Hood Barton, Stavertonbattery storage99application submitted6.2
Bidwell Solar Farmsolar farm5operational6.8
Court Barton Farm, Coffinswell Solar Farmsolar farm21approved, not built7.2
Barton Hill Industrial Parkbattery storage22.5operational7.5
Lower Blakemore Farmsolar farm5refused on appeal7.9
Parkview solar parksolar farm6.5operational8.6
Hazard Farmsolar farm6.4operational9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.466, -3.6445).