Energy Projects Near You

Solar, wind and battery projects near Totnes (TQ9)

23 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TQ9 (South Hams): 3 are waiting for a planning decision, 3 approved but not yet running, 8 operational. The largest live scheme is Hood Barton, Staverton (99 MW battery storage, application submitted on 12 December 2024, no decision recorded), 5.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

23projects within 10 km
3awaiting a decision
3approved, not running
8operational

Projects within 10 km of TQ9

Projects of 1 MW and more (17)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Totnes Community Wind Farmwind farmwind farm4.6refusedupdated Apr 2013Aug 2012refused Feb 2013Apr 2013South Hams1.3
Lower Blakemore Farmsolar farmsolar farm5refused on appealupdated Apr 2016Sep 2014refused Jun 2015Apr 2016South Hams3.1
Bidwell Solar Farmsolar farmsolar farm5operationalupdated Jul 2015May 2013granted Jul 2013Jul 2015South Hams3.8
Hazard Farmsolar farmsolar farm6.4operationalupdated Jun 2014Oct 2012granted May 2013Jun 2014South Hams5.0
Riverford Farmbattery storagebattery storage49.9permission expiredupdated Aug 2020Oct 2017granted Dec 2017Aug 2020South Hams5.8
Hood Barton, Stavertonbattery storagebattery storage99application submittedupdated Jan 2025Dec 2024—Jan 2025South Hams5.8
Colleen Farmsolar farmsolar farm2.2abandonedupdated Oct 2016Jun 2014granted Mar 2015Oct 2016South Hams5.9
Halwell Airfieldsolarsolar5.7refusedupdated Jan 2014Sep 2013refused Nov 2013Jan 2014South Hams6.0
Coombeshead Solar Farmsolar farmsolar farm8operationalupdated May 2018Jan 2014granted Aug 2014May 2018South Hams6.3
Waye Bartonsolar farmsolar farm5application withdrawnupdated Oct 2015Aug 2015—Oct 2015Teignbridge6.4
Hatchlands Farmsolar farmsolar farm5.2operationalupdated Mar 2013Aug 2012granted Oct 2012Mar 2013South Hams6.7
Blackawton Solar Farmsolar farmsolar farm3operationalupdated Dec 2014Dec 2013granted Mar 2014Dec 2014South Hams6.8
Place Barton Farmsolar farmsolar farm4.9operationalupdated Jun 2017Apr 2015granted Sep 2015Jun 2017South Hams7.4
Land at Oldstone Farmsolar farmsolar farm5operationalupdated Jun 2017Aug 2015granted Apr 2016Jun 2017South Hams7.5
Town Farm, Blackawtonbattery storagebattery storage3application withdrawnupdated May 2024Apr 2024—May 2024South Hams7.6
Marley Thatch Solar Farmsolar farmsolar farm6.3operationalupdated Apr 2013Mar 2012granted Jun 2012Apr 2013South Hams8.4
Brokenbury Farm, Galmpton Solar Farmsolar farmsolar farm2.7approved, not built may be out of dateupdated Dec 2022May 2021granted Nov 2022Dec 2022Torbay9.8
Smaller schemes under 1 MW, mostly rooftop solar (6)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Littlehempston Water Treatment Works, Littlehempstonsolar farmsolar farm—application submitted may be out of dateupdated Nov 2023Oct 2023—Nov 2023South Hams3.7
Daintons Storage, Yalberton Industrial Estatebattery storagebattery storage—application submitted may be out of dateupdated Aug 2022Aug 2022—Aug 2022Torbay7.1
South Devon College, Spots Hallrooftop solarrooftop solar0.3application withdrawnupdated Oct 2022Sep 2022—Oct 2022Torbay7.3
Morrisons, Totnes Roadrooftop solarrooftop solar0.3approved, not builtupdated Dec 2022Oct 2022granted Nov 2022Dec 2022Torbay7.7
Torbay Leisure Centre Energy Projectrooftop solarrooftop solar0.2under constructionupdated Feb 2022Feb 2022granted Mar 2022Feb 2022Torbay8.9
Totnes Road, Ipplepen - Micro Energy Storage Facilitybattery storagebattery storage0.2refusedupdated Jul 2025May 2025refused Jul 2025Jul 2025Teignbridge9.6

Distance from the average position of the TQ9 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm1311812.7
Rooftop solar302000.5
Solar100010
Wind farm100010
Battery storage5200199

MW in pipeline: pending, approved and under-construction capacity.

How South Hams decides solar, wind and battery applications

ApplicationsSouth HamsUK
Decided applications (solar, wind, battery)3610,236
Refused6 (17%)19%
Solar refused3 of 2812%
Onshore wind refused3 of 345%
Battery storage refused0 of 516%
Median time from submission to decision13.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

All projects in South Hams

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TQ9, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.