Halwell Airfield (5.7 MW solar)

Halwell Airfield is a 5.7 MW solar project in South Hams, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 22 November 2013; the record was last updated on 24 January 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.7 MWsolar
refusedstatus in REPD
24 January 2014record last updated
South Hamscouncil area

Planning timeline

DateStage
3 September 2013Application submitted
22 November 2013Refused by the planning authority

Project details

Technology
solar
Capacity
5.7 MW
Status (REPD)
refused
Record last updated
24 January 2014
Operator or applicant
Lightsource Renewable Energy
Planning authority
South Hams
Planning application reference
22/2050/13/F
Address (REPD)
Land at SX786 529, South of Halwell Airfield, Halwell
Council area (by location)
South Hams
Time to decision
11 weeks
REPD reference
1373

Who decides

ApplicationsSouth HamsUK
Decided applications (solar, wind, battery)3610,236
Refused6 (17%)19%
Solar refused3 of 2812%
Onshore wind refused3 of 345%
Battery storage refused0 of 516%
Median time from submission to decision13.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at Oldstone Farmsolar farm5operational3.5
Coombeshead Solar Farmsolar farm8operational4.8
Lower Blakemore Farmsolar farm5refused on appeal6.9
Hazard Farmsolar farm6.4operational7.4
Bidwell Solar Farmsolar farm5operational8.6
Hatchlands Farmsolar farm5.2operational8.6
Marley Thatch Solar Farmsolar farm6.3operational9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.3634, -3.7081).