Coombeshead Solar Farm (8 MW)

Coombeshead Solar Farm is an 8 MW solar farm project in South Hams, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 March 2015; the record was last updated on 2 May 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8 MWsolar farm
operationalstatus in REPD
2 May 2018record last updated
South Hamscouncil area

Planning timeline

DateStage
31 January 2014Application submitted
29 August 2014Planning permission granted
1 September 2014Construction started
15 March 2015Operational

Project details

Technology
solar farm
Capacity
8 MW
Status (REPD)
operational
Record last updated
2 May 2018
Operator or applicant
Foresight
Planning authority
South Hams
Planning application reference
17/0265/14/F
Site area
23.4 ha
Address (REPD)
Coombeshead Farm Diptford
Council area (by location)
South Hams
Time to decision
30 weeks
REPD reference
2331

Who decides

ApplicationsSouth HamsUK
Decided applications (solar, wind, battery)3610,236
Refused6 (17%)19%
Solar refused3 of 2812%
Onshore wind refused3 of 345%
Battery storage refused0 of 516%
Median time from submission to decision13.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hazard Farmsolar farm6.4operational3.8
Hatchlands Farmsolar farm5.2operational4.4
Lower Blakemore Farmsolar farm5refused on appeal4.8
Halwell Airfieldsolar5.7refused4.8
Marley Thatch Solar Farmsolar farm6.3operational5.3
Bidwell Solar Farmsolar farm5operational6.4
Land at Oldstone Farmsolar farm5operational8.3
Riverford Farmbattery storage49.9permission expired8.8
Hood Barton, Stavertonbattery storage99application submitted8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.386, -3.7664).