Hatchlands Farm (5.2 MW solar farm)

Hatchlands Farm is a 5.2 MW solar farm project in South Hams, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 25 March 2013; the record was last updated on 11 March 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.2 MWsolar farm
operationalstatus in REPD
11 March 2013record last updated
South Hamscouncil area

Planning timeline

DateStage
1 August 2012Application submitted
23 October 2012Planning permission granted
3 December 2012Construction started
25 March 2013Operational

Project details

Technology
solar farm
Capacity
5.2 MW
Status (REPD)
operational
Record last updated
11 March 2013
Operator or applicant
Orta Solar
Planning authority
South Hams
Planning application reference
23/1754/12/F
Address (REPD)
Haberton, Totnes
Council area (by location)
South Hams
Time to decision
12 weeks
REPD reference
1176

Who decides

ApplicationsSouth HamsUK
Decided applications (solar, wind, battery)3610,236
Refused6 (17%)19%
Solar refused3 of 2812%
Onshore wind refused3 of 345%
Battery storage refused0 of 516%
Median time from submission to decision13.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Marley Thatch Solar Farmsolar farm6.3operational1.7
Hazard Farmsolar farm6.4operational1.7
Lower Blakemore Farmsolar farm5refused on appeal3.6
Bidwell Solar Farmsolar farm5operational4.2
Coombeshead Solar Farmsolar farm8operational4.4
Hood Barton, Stavertonbattery storage99application submitted5.7
Riverford Farmbattery storage49.9permission expired5.7
Halwell Airfieldsolar5.7refused8.6
Parkview solar parksolar farm6.5operational9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.4236, -3.7849).