Hood Barton, Staverton (99 MW battery storage)

Hood Barton, Staverton is a 99 MW battery storage project in South Hams, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 12 December 2024, no decision recorded; the record was last updated on 17 January 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

99 MWbattery storage
application submittedstatus in REPD
17 January 2025record last updated
South Hamscouncil area

Planning timeline

DateStage
12 December 2024Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
99 MW
Status (REPD)
application submitted
Record last updated
17 January 2025
Operator or applicant
Energy Planning
Planning authority
South Hams
Planning application reference
3628/24/FUL
Address (REPD)
Hood Barton, Staverton, Totnes
Council area (by location)
South Hams
Name in REPD
Hood Barton, Staverton - Battery Energy Storage System
REPD reference
17261

Who decides

ApplicationsSouth HamsUK
Decided applications (solar, wind, battery)3610,236
Refused6 (17%)19%
Solar refused3 of 2812%
Onshore wind refused3 of 345%
Battery storage refused0 of 516%
Median time from submission to decision13.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Riverford Farmbattery storage49.9permission expired<0.1
Bidwell Solar Farmsolar farm5operational2.5
Lower Blakemore Farmsolar farm5refused on appeal4.3
Parkview solar parksolar farm6.5operational4.9
Hazard Farmsolar farm6.4operational5.1
Hatchlands Farmsolar farm5.2operational5.7
Waye Bartonsolar farm5application withdrawn6.2
Marley Thatch Solar Farmsolar farm6.3operational6.9
Rydon Farmsolar farm12operational8.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.4619, -3.732).