Energy Projects Near You

Higher Humber Farm (5.9 MW solar farm)

Higher Humber Farm is a 5.9 MW solar farm project in Teignbridge, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 9 February 2017; the record was last updated on 28 February 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.9 MWsolar farm
refused on appealstatus in REPD
28 February 2017record last updated
Teignbridgecouncil area

Planning timeline

DateStage
6 January 2015Application submitted
5 April 2016Refused by the planning authority
12 May 2016Appeal lodged
9 February 2017Appeal refused

Project details

Technology
solar farm
Capacity
5.9 MW
Status (REPD)
refused on appeal
Record last updated
28 February 2017
Operator or applicant
TGC Renewables
Planning authority
Teignbridge
Planning application reference
14/03725/MAJ
Appeal reference
APP/P1133/W/16/3148497
Site area
17.5 ha
Address (REPD)
Humber Lane, Bishopsteignton, Devon
Council area (by location)
Teignbridge
Time to decision
65 weeks
REPD reference
6130

Who decides

ApplicationsTeignbridgeUK
Decided applications (solar, wind, battery)1410,236
Refused5 (36%)19%
Solar refused4 of 1212%
Battery storage refused1 of 216%
Median time from submission to decision12.4 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Sawmills Solar Farmsolar farm6.5operational4.3
Apple Tree Closesolar farm5approved, not built5.7
Court Barton Farm, Coffinswell Solar Farmsolar farm21approved, not built6.4
Rydon Farmsolar farm12operational7.6
Barton Hill Industrial Parkbattery storage22.5operational8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.5626, -3.5724).