Solar, wind and battery projects near Exmouth (EX8)
21 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of EX8 (East Devon): 4 are waiting for a planning decision, 7 approved but not yet running, 3 operational. The largest live scheme is Blackhill Quarry, Woodbury (60 MW battery storage, approved on 13 July 2023, not yet built; REPD status may be out of date), 4.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of EX8
Projects of 1 MW and more (11)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Liverton Farmsolar farm | solar farm | 4.8 | operationalupdated Mar 2015 | Oct 2013 | granted Jan 2014 | Mar 2015 | East Devon | 2.2 |
| Bystock Solar Farmsolar farm | solar farm | 4.1 | operationalupdated May 2015 | Jul 2014 | granted Sep 2014 | May 2015 | East Devon | 2.4 |
| Veiges Farm Solar Parksolar farm | solar farm | 5 | abandonedupdated Feb 2019 | Sep 2015 | granted Feb 2016 | Feb 2019 | East Devon | 2.9 |
| Coombe Farmsolar farm | solar farm | 8 | operationalupdated Jun 2015 | May 2014 | granted Sep 2014 | Jun 2015 | East Devon | 3.2 |
| Blackhill Quarry, Woodburybattery storage | battery storage | 60 | approved, not built may be out of dateupdated Aug 2023 | Nov 2022 | granted Jul 2023 | Aug 2023 | East Devon | 4.2 |
| Higher Bagmore Farm, Ebford Lane -Battery Energy Storage Systembattery storage | battery storage | 50 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | East Devon | 5.4 |
| Kenniford Farmsolar farm | solar farm | 4 | abandonedupdated Sep 2018 | Jan 2015 | granted Oct 2015 | Sep 2018 | East Devon | 7.5 |
| Westexe, Greendale Business Parkrooftop solar | rooftop solar | 1.1 | approved, not builtupdated Feb 2024 | Jan 2024 | granted Feb 2024 | Feb 2024 | East Devon | 7.8 |
| Orchard Parksolar farm | solar farm | 5.1 | refused on appealupdated Oct 2016 | Dec 2014 | refused Dec 2015 | Oct 2016 | East Devon | 8.3 |
| Winslade Parksolar farm | solar farm | 1.9 | approved, not builtupdated Mar 2025 | Jan 2024 | refused May 2024 | Mar 2025 | East Devon | 8.7 |
| Higher Hawkerland Farm, Sidmouth Road Solar Farmsolar farm | solar farm | 18 | approved, not builtupdated Mar 2023 | Oct 2022 | granted Apr 2023 | Mar 2023 | East Devon | 8.7 |
Smaller schemes under 1 MW, mostly rooftop solar (10)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Bradham Lane - Micro Energy Storagebattery storage | battery storage | 0.2 | application withdrawnupdated Apr 2026 | Jan 2026 | — | Apr 2026 | East Devon | 0.9 |
| Lower Veiges Plantationbattery storage | battery storage | — | abandonedupdated Feb 2019 | Dec 2015 | — | Feb 2019 | East Devon | 2.9 |
| Devon Cliffs Holiday Centre, Sandy Bayrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Mar 2023 | Feb 2023 | granted Mar 2023 | Mar 2023 | East Devon | 3.0 |
| Langdon Hospital, Langdonsolar farm | solar farm | — | application submittedupdated Dec 2025 | Nov 2025 | — | Dec 2025 | Teignbridge | 5.8 |
| Langdon Hospital, Langdonbattery storage | battery storage | — | application submittedupdated Dec 2025 | Nov 2025 | — | Dec 2025 | Teignbridge | 5.8 |
| Darts Farm Shopping Village, Clyst St Georgerooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Mar 2023 | Feb 2023 | granted Mar 2023 | Mar 2023 | East Devon | 7.1 |
| Greendale Business Park, Woodbury Salterton Battery Farmbattery storage | battery storage | — | refusedupdated Jun 2025 | Jan 2025 | refused May 2025 | Jun 2025 | East Devon | 7.8 |
| Old Teignmouth Road - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | application withdrawnupdated Sep 2024 | Jul 2024 | — | Sep 2024 | Teignbridge | 8.2 |
| Hill Barton Business Park, Clyst St Marybattery storage | battery storage | 0.2 | application submitted may be out of dateupdated Jul 2024 | Jun 2024 | — | Jul 2024 | East Devon | 8.8 |
| Crealy Adventure Park, Clyst St Marysolar farm | solar farm | 0.9 | approved, not built may be out of dateupdated Oct 2022 | Aug 2022 | granted Sep 2022 | Oct 2022 | East Devon | 8.8 |
Distance from the average position of the EX8 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 10 | 1 | 3 | 3 | 1 | 20.8 |
| Rooftop solar | 3 | 0 | 3 | 0 | 0 | 1.8 |
| Battery storage | 8 | 3 | 1 | 0 | 1 | 110 |
MW in pipeline: pending, approved and under-construction capacity.
How East Devon decides solar, wind and battery applications
| Applications | East Devon | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 55 | 10,236 |
| Refused | 17 (31%) | 19% |
| Solar refused | 9 of 36 | 12% |
| Battery storage refused | 8 of 19 | 16% |
| Median time from submission to decision | 21.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 3 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near EX8, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.