Energy Projects Near You

Renewable energy projects in East Devon

60 solar, wind or battery projects of 150 kW or more are located in East Devon (REPD, July 2026 extract): 5 pending, 24 approved but not running, 15 operational and 11 refused. The council refused 17 of 55 decided applications (31%; UK 19%), with a median 21 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

60projects in the council area
5awaiting a decision
24approved, not running
31%of decisions refused

How East Devon decides

ApplicationsEast DevonUK
Decided applications (solar, wind, battery)5510,236
Refused17 (31%)19%
Solar refused9 of 3612%
Battery storage refused8 of 1916%
Median time from submission to decision21.0 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

Projects in East Devon

Projects of 1 MW and more (44)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Saundercroft Farmbattery storagebattery storage290approved, not builtupdated Feb 2024May 2023granted Jan 2024Feb 2024
Stammery Hillbattery storagebattery storage150refusedupdated Jun 2025Jun 2024refused May 2025Jun 2025
Exeter Substation, Broadclystbattery storagebattery storage125approved, not builtupdated Jun 2026May 2025granted May 2026Jun 2026
Pound Road, Hawkchurchbattery storagebattery storage120refusedupdated Oct 2022Oct 2022refused Feb 2024Oct 2022
Pound Road, Hawkchurchbattery storagebattery storage120refusedupdated Aug 2023May 2023refused Aug 2023Aug 2023
National Grid Substationbattery storagebattery storage100approved, not builtupdated Sep 2025Oct 2024granted Aug 2025Sep 2025
Newlands Farm, Crewkerne Roadbattery storagebattery storage80refusedupdated Oct 2025Dec 2024refused Sep 2025Oct 2025
Blackhill Quarry, Woodburybattery storagebattery storage60approved, not built may be out of dateupdated Aug 2023Nov 2022granted Jul 2023Aug 2023
Saundercroft Road, Broadclystbattery storagebattery storage57approved, not builtupdated Aug 2025Jan 2025granted Jul 2025Aug 2025
Wareham Road, Scouse Farmbattery storagebattery storage50refusedupdated Jul 2025Oct 2024refused Jun 2025Jul 2025
Higher Bagmore Farm, Ebford Lane -Battery Energy Storage Systembattery storagebattery storage50application submittedupdated Sep 2025Jul 2025—Sep 2025
National Grid Axminster Substationbattery storagebattery storage49.9application submitted may be out of dateupdated Sep 2020Sep 2020—Sep 2020
Rutton Farm, Whimple - Horton Solar Farmsolar farmsolar farm49.9approved, not built may be out of dateupdated Mar 2026May 2022granted Jun 2023Mar 2026
Paytherden Solar Farm (Peradon)solar farmsolar farm49under constructionupdated Jul 2022Dec 2021granted Dec 2022Jul 2022
Escot Park Estate, Talaton Solar Farmsolar farmsolar farm35application submittedupdated Oct 2025Aug 2025—Oct 2025
Ford Oaks Solar & Green Infrastructure Facilitysolar farmsolar farm30under constructionupdated Feb 2026May 2022granted Nov 2023Feb 2026
Beavor - Photovoltaic Solar Arrayssolar farmsolar farm18.9under constructionupdated Mar 2023Nov 2021granted Feb 2022Mar 2023
Higher Hawkerland Farm, Sidmouth Road Solar Farmsolar farmsolar farm18approved, not builtupdated Mar 2023Oct 2022granted Apr 2023Mar 2023
Kerswell Barton Farm, Broadclystsolar farmsolar farm16.2approved, not builtupdated Sep 2025Mar 2025granted Aug 2025Sep 2025
Rockbeare Hillsolar farmsolar farm15approved, not built may be out of dateupdated Sep 2020Jan 2020granted Jul 2020Sep 2020
Crannaford Solar Farmsolar farmsolar farm12.5operationalupdated Aug 2014Feb 2013granted Sep 2013Aug 2014
Great Houndbeare Farmsolar farmsolar farm10operationalupdated Jul 2018Jul 2013granted Nov 2013Jul 2018
Stonebarrow Farmsolar farmsolar farm8operationalupdated Aug 2014Nov 2012granted Apr 2013Aug 2014
Coombe Farmsolar farmsolar farm8operationalupdated Jun 2015May 2014granted Sep 2014Jun 2015
East Hill Stripssolarsolar7refusedupdated Jun 2014Feb 2014refused May 2014Jun 2014
Saundercroft Solar Farmsolar farmsolar farm7operationalupdated Jul 2018Oct 2012granted Jan 2013Jul 2018
Dunkeswell Airfieldbattery storagebattery storage6.5approved, not built may be out of dateupdated Nov 2021Sep 2021granted Nov 2021Nov 2021
Poltimore solar farmsolar farmsolar farm5.5refusedupdated Feb 2014Jul 2013refused Dec 2013Feb 2014
Orchard Parksolar farmsolar farm5.1refused on appealupdated Oct 2016Dec 2014refused Dec 2015Oct 2016
Pithayessolarsolar5refusedupdated Sep 2015Jun 2013refused Nov 2013Sep 2015
Newlands Farm (East Devon)solar farmsolar farm5operationalupdated Apr 2013Jul 2012granted Nov 2012Apr 2013
Burrowton Farmsolar farmsolar farm5operationalupdated Jul 2018Apr 2011granted Oct 2011Jul 2018
Axe View Solar Farmsolar farmsolar farm5operationalupdated Mar 2018Mar 2015granted Apr 2016Mar 2018
Veiges Farm Solar Parksolar farmsolar farm5abandonedupdated Feb 2019Sep 2015granted Feb 2016Feb 2019
Strete Farm Solar Farmsolar farmsolar farm4.8operationalupdated Apr 2013May 2012granted Aug 2012Apr 2013
Liverton Farmsolar farmsolar farm4.8operationalupdated Mar 2015Oct 2013granted Jan 2014Mar 2015
Wyld Meadow Solar Farmsolar farmsolar farm4.8operationalupdated Jul 2018Apr 2011granted Jul 2011Jul 2018
Bystock Solar Farmsolar farmsolar farm4.1operationalupdated May 2015Jul 2014granted Sep 2014May 2015
Beechgrove Farmsolar farmsolar farm4operationalupdated Oct 2013Mar 2011granted May 2011Oct 2013
St Francis Court Farmsolar farmsolar farm4operationalupdated Mar 2017Nov 2013granted May 2014Mar 2017
Kenniford Farmsolar farmsolar farm4abandonedupdated Sep 2018Jan 2015granted Oct 2015Sep 2018
Dunkeswell Airfieldsolar farmsolar farm2operationalupdated May 2015Aug 2013granted Mar 2014May 2015
Winslade Parksolar farmsolar farm1.9approved, not builtupdated Mar 2025Jan 2024refused May 2024Mar 2025
Westexe, Greendale Business Parkrooftop solarrooftop solar1.1approved, not builtupdated Feb 2024Jan 2024granted Feb 2024Feb 2024
Smaller schemes under 1 MW, mostly rooftop solar (16)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Crealy Adventure Park, Clyst St Marysolar farmsolar farm0.9approved, not built may be out of dateupdated Oct 2022Aug 2022granted Sep 2022Oct 2022
Devon Cliffs Holiday Centre, Sandy Bayrooftop solarrooftop solar0.5approved, not builtupdated Mar 2023Feb 2023granted Mar 2023Mar 2023
Skypark, Spitfire Avenuerooftop solarrooftop solar0.5approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026
Darts Farm Shopping Village, Clyst St Georgerooftop solarrooftop solar0.2approved, not built may be out of dateupdated Mar 2023Feb 2023granted Mar 2023Mar 2023
Electricity Sub Station, Babbage Way - Micro Energy Storage Facilitybattery storagebattery storage0.2application withdrawnupdated Sep 2024Jun 2024—Sep 2024
Hill Barton Business Park, Clyst St Marybattery storagebattery storage0.2application submitted may be out of dateupdated Jul 2024Jun 2024—Jul 2024
Wares Farm, Clyst Honiton - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Oct 2024Jul 2024granted Oct 2024Oct 2024
Blackhorse Lane - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Oct 2024Aug 2024granted Oct 2024Oct 2024
Exteter Airport, London Road - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Feb 2025Dec 2024granted Feb 2025Feb 2025
Bradham Lane - Micro Energy Storagebattery storagebattery storage0.2application withdrawnupdated Apr 2026Jan 2026—Apr 2026
Broadhayes Farm, Stocklandsolar farmsolar farm0.2application submittedupdated Jan 2026Dec 2025—Jan 2026
Lower Veiges Plantationbattery storagebattery storage—abandonedupdated Feb 2019Dec 2015—Feb 2019
Hawkchurchbattery storagebattery storage—refusedupdated Sep 2025Mar 2022refused Aug 2025Sep 2025
Axe View Solar Farm, Wadbrookbattery storagebattery storage—approved, not built may be out of dateupdated Apr 2022Mar 2022granted Mar 2023Apr 2022
Wyld Meadow Farmbattery storagebattery storage—approved, not built may be out of dateupdated May 2022May 2022granted Jul 2022May 2022
Greendale Business Park, Woodbury Salterton Battery Farmbattery storagebattery storage—refusedupdated Jun 2025Jan 2025refused May 2025Jun 2025

Postcode districts in East Devon

DistrictProjects within 10 kmPendingApprovedOperational
EX5565349
EX821473
EX915253
EX107042
EX11242145
EX120000
EX1322238
EX145211
EX241100

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to East Devon by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.