Energy Projects Near You

Rockbeare Hill (15 MW solar farm)

Rockbeare Hill is a 15 MW solar farm project in East Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 30 July 2020, not yet built; the record was last updated on 30 September 2020. REPD records the planning permission as expiring on 30 July 2023, but the project holds a Contracts for Difference award (AR4), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWsolar farm
approved, not builtmay be out of datestatus in REPD
30 September 2020record last updated
East Devoncouncil area

REPD records the planning permission as expiring on 30 July 2023, but the project holds a Contracts for Difference award (AR4), so construction may have started.

Planning timeline

DateStage
10 January 2020Application submitted
30 July 2020Planning permission granted
30 July 2023Permission expired

Project details

Technology
solar farm
Capacity
15 MW
Status (REPD)
approved, not built
Record last updated
30 September 2020
Operator or applicant
Spring Che
Planning authority
East Devon
Planning application reference
19/2832/MFUL
Site area
25.9 ha
Address (REPD)
Land To The South Of, Rockbeare Hill, Rockbeare, Exeter, Devon
Council area (by location)
East Devon
Time to decision
29 weeks
Contracts for Difference
AR4
REPD reference
7815

Who decides

ApplicationsEast DevonUK
Decided applications (solar, wind, battery)5510,236
Refused17 (31%)19%
Solar refused9 of 3612%
Battery storage refused8 of 1916%
Median time from submission to decision21.0 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Great Houndbeare Farmsolar farm10operational0.7
Ford Oaks Solar & Green Infrastructure Facilitysolar farm30under construction1.3
Pithayessolar5refused3.6
Higher Hawkerland Farm, Sidmouth Road Solar Farmsolar farm18approved, not built3.7
Rutton Farm, Whimple - Horton Solar Farmsolar farm49.9approved, not built5.0
Saundercroft Farmbattery storage290approved, not built5.1
Saundercroft Road, Broadclystbattery storage57approved, not built5.1
Saundercroft Solar Farmsolar farm7operational5.2
Crannaford Solar Farmsolar farm12.5operational5.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7351, -3.3419).