Energy Projects Near You

Higher Hawkerland Farm, Sidmouth Road Solar Farm (18 MW)

Higher Hawkerland Farm, Sidmouth Road Solar Farm is an 18 MW solar farm project in East Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 28 April 2023, not yet built; the record was last updated on 29 March 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18 MWsolar farm
approved, not builtstatus in REPD
29 March 2023record last updated
East Devoncouncil area

Planning timeline

DateStage
28 October 2022Application submitted
28 April 2023Planning permission granted

Project details

Technology
solar farm
Capacity
18 MW
Status (REPD)
approved, not built
Record last updated
29 March 2023
Operator or applicant
Spring Dev 09 Limited
Planning authority
East Devon
Planning application reference
22/2409/MFUL
Site area
22.8 ha
Address (REPD)
Higher Hawkerland Farm Sidmouth Road Aylesbeare
Council area (by location)
East Devon
Time to decision
26 weeks
Contracts for Difference
AR6
Name in REPD
Higher Hawkerland Farm, Sidmouth Road - Solar Farm
REPD reference
12578

Who decides

ApplicationsEast DevonUK
Decided applications (solar, wind, battery)5510,236
Refused17 (31%)19%
Solar refused9 of 3612%
Battery storage refused8 of 1916%
Median time from submission to decision21.0 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Great Houndbeare Farmsolar farm10operational3.4
Ford Oaks Solar & Green Infrastructure Facilitysolar farm30under construction3.4
Rockbeare Hillsolar farm15approved, not built3.7
Blackhill Quarry, Woodburybattery storage60approved, not built4.6
Higher Bagmore Farm, Ebford Lane -Battery Energy Storage Systembattery storage50application submitted5.2
Orchard Parksolar farm5.1refused on appeal5.6
Coombe Farmsolar farm8operational5.6
Veiges Farm Solar Parksolar farm5abandoned6.3
Pithayessolar5refused6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7025, -3.3543).