Energy Projects Near You

Ford Oaks Solar & Green Infrastructure Facility (30 MW)

Ford Oaks Solar & Green Infrastructure Facility is a 30 MW solar farm project in East Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 October 2025; the record was last updated on 17 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWsolar farm
under constructionstatus in REPD
17 February 2026record last updated
East Devoncouncil area

Planning timeline

DateStage
19 May 2022Application submitted
12 January 2023Refused by the planning authority
20 April 2023Appeal lodged
30 November 2023Planning permission granted
30 November 2023Appeal allowed
1 October 2025Construction started

Project details

Technology
solar farm
Capacity
30 MW
Status (REPD)
under construction
Record last updated
17 February 2026
Operator or applicant
Low Carbon Alliance / Taiyo Power & Storage
Planning authority
East Devon
Planning application reference
22/0990/MFUL
Appeal reference
APP/U1105/W/23/3320714
Site area
74.8 ha
Address (REPD)
Marsh Green Farm Marsh Green, Exeter
Council area (by location)
East Devon
Time to decision
80 weeks
Contracts for Difference
AR7a
REPD reference
11366

Who decides

ApplicationsEast DevonUK
Decided applications (solar, wind, battery)5510,236
Refused17 (31%)19%
Solar refused9 of 3612%
Battery storage refused8 of 1916%
Median time from submission to decision21.0 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Great Houndbeare Farmsolar farm10operational0.6
Rockbeare Hillsolar farm15approved, not built1.3
Higher Hawkerland Farm, Sidmouth Road Solar Farmsolar farm18approved, not built3.4
Pithayessolar5refused3.5
Crannaford Solar Farmsolar farm12.5operational4.3
Saundercroft Farmbattery storage290approved, not built4.4
Saundercroft Road, Broadclystbattery storage57approved, not built4.4
Saundercroft Solar Farmsolar farm7operational4.5
Exeter Substation, Broadclystbattery storage125approved, not built4.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.733, -3.3603).