Energy Projects Near You

Solar, wind and battery projects near Sidmouth (EX10)

7 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of EX10 (East Devon): 4 approved but not yet running, 2 operational. The largest live scheme is Blackhill Quarry, Woodbury (60 MW battery storage, approved on 13 July 2023, not yet built; REPD status may be out of date), 9.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7projects within 10 km
0awaiting a decision
4approved, not running
2operational

Projects within 10 km of EX10

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
East Hill Stripssolarsolar7refusedupdated Jun 2014Feb 2014refused May 2014Jun 2014East Devon4.5
Higher Hawkerland Farm, Sidmouth Road Solar Farmsolar farmsolar farm18approved, not builtupdated Mar 2023Oct 2022granted Apr 2023Mar 2023East Devon7.6
Rockbeare Hillsolar farmsolar farm15approved, not built may be out of dateupdated Sep 2020Jan 2020granted Jul 2020Sep 2020East Devon8.2
Great Houndbeare Farmsolar farmsolar farm10operationalupdated Jul 2018Jul 2013granted Nov 2013Jul 2018East Devon8.6
Ford Oaks Solar & Green Infrastructure Facilitysolar farmsolar farm30under constructionupdated Feb 2026May 2022granted Nov 2023Feb 2026East Devon9.1
Blackhill Quarry, Woodburybattery storagebattery storage60approved, not built may be out of dateupdated Aug 2023Nov 2022granted Jul 2023Aug 2023East Devon9.6
Strete Farm Solar Farmsolar farmsolar farm4.8operationalupdated Apr 2013May 2012granted Aug 2012Apr 2013East Devon9.8

Distance from the average position of the EX10 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm5032063
Solar100010
Battery storage1010060

MW in pipeline: pending, approved and under-construction capacity.

How East Devon decides solar, wind and battery applications

ApplicationsEast DevonUK
Decided applications (solar, wind, battery)5510,236
Refused17 (31%)19%
Solar refused9 of 3612%
Battery storage refused8 of 1916%
Median time from submission to decision21.0 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

All projects in East Devon

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near EX10, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.