Energy Projects Near You

Solar, wind and battery projects near Honiton (EX14)

5 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of EX14 (East Devon): 2 are waiting for a planning decision, 1 approved but not yet running, 1 operational. The largest live scheme is Escot Park Estate, Talaton Solar Farm (35 MW solar farm, application submitted on 22 August 2025, no decision recorded), 8.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5projects within 10 km
2awaiting a decision
1approved, not running
1operational

Projects within 10 km of EX14

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Dunkeswell Airfieldbattery storagebattery storage6.5approved, not built may be out of dateupdated Nov 2021Sep 2021granted Nov 2021Nov 2021East Devon6.1
Dunkeswell Airfieldsolar farmsolar farm2operationalupdated May 2015Aug 2013granted Mar 2014May 2015East Devon6.1
Escot Park Estate, Talaton Solar Farmsolar farmsolar farm35application submittedupdated Oct 2025Aug 2025—Oct 2025East Devon8.6
East Hill Stripssolarsolar7refusedupdated Jun 2014Feb 2014refused May 2014Jun 2014East Devon9.9
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Broadhayes Farm, Stocklandsolar farmsolar farm0.2application submittedupdated Jan 2026Dec 2025—Jan 2026East Devon7.2

Distance from the average position of the EX14 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm3201035.2
Solar100010
Battery storage101006.5

MW in pipeline: pending, approved and under-construction capacity.

How East Devon decides solar, wind and battery applications

ApplicationsEast DevonUK
Decided applications (solar, wind, battery)5510,236
Refused17 (31%)19%
Solar refused9 of 3612%
Battery storage refused8 of 1916%
Median time from submission to decision21.0 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

All projects in East Devon

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near EX14, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.