Solar, wind and battery projects near Cullompton (EX15)
27 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of EX15 (Mid Devon): 3 are waiting for a planning decision, 8 approved but not yet running, 12 operational. The largest live scheme is Junction 27, Westleigh (400 MW battery storage, approved on 12 April 2024, not yet built), 7.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of EX15
Projects of 1 MW and more (22)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Higher Pirzwell Solar Farmsolar farm | solar farm | 1.2 | operationalupdated Oct 2013 | Mar 2012 | granted May 2012 | Oct 2013 | Mid Devon | 1.9 |
| Langlands Solar Farmsolar farm | solar farm | 2.1 | operationalupdated Feb 2014 | May 2012 | granted Aug 2012 | Feb 2014 | Mid Devon | 2.6 |
| Stoneshill Farmsolar farm | solar farm | 5 | operationalupdated Nov 2017 | Nov 2014 | granted Feb 2016 | Nov 2017 | Mid Devon | 3.0 |
| Dean Hill Road Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Sep 2024 | Jan 2023 | granted Nov 2023 | Sep 2024 | Mid Devon | 3.2 |
| Broad Pathsolar farm | solar farm | 4.3 | application submittedupdated Feb 2025 | Jan 2025 | — | Feb 2025 | Mid Devon | 4.3 |
| Venn Farmsolar farm | solar farm | 1 | abandonedupdated May 2016 | Oct 2013 | granted Feb 2014 | May 2016 | Mid Devon | 4.5 |
| Nether Mill Farmsolar farm | solar farm | 3.1 | operationalupdated Nov 2014 | Oct 2012 | granted Feb 2014 | Nov 2014 | Mid Devon | 4.5 |
| Broadpath Landfillsolar farm | solar farm | 5 | abandonedupdated Jan 2018 | Sep 2015 | granted Dec 2015 | Jan 2018 | Mid Devon | 4.5 |
| Great Curham Farmsolar farm | solar farm | 8 | refusedupdated Sep 2014 | Jun 2014 | refused Aug 2014 | Sep 2014 | Mid Devon | 5.3 |
| Kia Ora Farmsolar farm | solar farm | 1.8 | operationalupdated Apr 2013 | Sep 2012 | granted Nov 2012 | Apr 2013 | Mid Devon | 5.3 |
| Little Toms Solar Farmsolar farm | solar farm | 5 | under constructionupdated Jul 2025 | Nov 2023 | granted Jun 2024 | Jul 2025 | Mid Devon | 5.5 |
| Ayshford Court Farmsolar farm | solar farm | 5 | operationalupdated Jun 2013 | Dec 2010 | granted Jun 2011 | Jun 2013 | Mid Devon | 6.1 |
| Langford Solar Farmsolar farm | solar farm | 35 | operationalupdated Jul 2025 | Oct 2019 | granted Dec 2022 | Jul 2025 | Mid Devon | 6.4 |
| Langford Solar Farmbattery storage | battery storage | 35 | operationalupdated Jul 2025 | Nov 2018 | granted Dec 2022 | Jul 2025 | Mid Devon | 6.4 |
| Winham Farmsolar farm | solar farm | 5 | operationalupdated Feb 2016 | Apr 2014 | granted Jul 2014 | Feb 2016 | Mid Devon | 7.1 |
| Junction 27, Westleighbattery storage | battery storage | 400 | approved, not builtupdated Apr 2024 | Sep 2023 | granted Apr 2024 | Apr 2024 | Mid Devon | 7.3 |
| Barton Solar Farmsolar farm | solar farm | 1.2 | operationalupdated Nov 2012 | Mar 2012 | granted May 2012 | Nov 2012 | Mid Devon | 7.9 |
| Paytherden Solar Farm (Peradon)solar farm | solar farm | 49 | under constructionupdated Jul 2022 | Dec 2021 | granted Dec 2022 | Jul 2022 | East Devon | 8.0 |
| Dunkeswell Airfieldbattery storage | battery storage | 6.5 | approved, not built may be out of dateupdated Nov 2021 | Sep 2021 | granted Nov 2021 | Nov 2021 | East Devon | 8.2 |
| Dunkeswell Airfieldsolar farm | solar farm | 2 | operationalupdated May 2015 | Aug 2013 | granted Mar 2014 | May 2015 | East Devon | 8.2 |
| Red Hill Farmsolar farm | solar farm | 4.8 | operationalupdated Feb 2016 | Nov 2014 | granted Feb 2015 | Feb 2016 | Mid Devon | 9.1 |
| Wiseburrow Farmsolar farm | solar farm | 6 | refused on appealupdated Jul 2016 | Jul 2015 | refused Dec 2015 | Jul 2016 | Mid Devon | 9.1 |
Smaller schemes under 1 MW, mostly rooftop solar (5)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Homeleigh Solar Photovoltaics Panelsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | Mid Devon | 1.6 |
| Donaldson Timber Engineering, Kentisbearerooftop solar | rooftop solar | 0.1 | approved, not builtupdated Apr 2025 | Feb 2025 | granted Mar 2025 | Apr 2025 | Mid Devon | 2.3 |
| Broad Pathbattery storage | battery storage | — | application submittedupdated Feb 2025 | Jan 2025 | — | Feb 2025 | Mid Devon | 4.3 |
| Hunters Way, Culmstock Energy Storage Facilitybattery storage | battery storage | 0.2 | application submittedupdated Aug 2024 | Aug 2024 | — | Aug 2024 | Mid Devon | 6.5 |
| Hepco Slide Systems Roof PVrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2021 | May 2021 | granted Jun 2021 | Sep 2021 | Mid Devon | 9.5 |
Distance from the average position of the EX15 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 19 | 1 | 3 | 11 | 2 | 108 |
| Rooftop solar | 3 | 0 | 3 | 0 | 0 | 0.5 |
| Battery storage | 5 | 2 | 2 | 1 | 0 | 407 |
MW in pipeline: pending, approved and under-construction capacity.
How Mid Devon decides solar, wind and battery applications
| Applications | Mid Devon | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 39 | 10,236 |
| Refused | 13 (33%) | 19% |
| Solar refused | 11 of 34 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Battery storage refused | 1 of 4 | 16% |
| Median time from submission to decision | 13.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 8 / 5 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near EX15, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.