Energy Projects Near You

Langford Solar Farm (35 MW)

Langford Solar Farm is a 35 MW solar farm project in Mid Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 2 July 2025; the record was last updated on 28 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

35 MWsolar farm
operationalstatus in REPD
28 July 2025record last updated
Mid Devoncouncil area

Planning timeline

DateStage
10 October 2019Application submitted
23 September 2021Refused by the planning authority
17 February 2022Appeal lodged
5 December 2022Planning permission granted
5 December 2022Appeal allowed
2 July 2025Operational

Project details

Technology
solar farm
Capacity
35 MW
Status (REPD)
operational
Record last updated
28 July 2025
Operator or applicant
JBM Solar Projects
Planning authority
Mid Devon
Planning application reference
19/01679/MFUL
Appeal reference
APP/Y1138/W/22/3293104
Site area
60.8 ha
Address (REPD)
Land at NGR 303437 103555 East, Langford Mill and Tye Farm, Cullompton, Devon
Council area (by location)
Mid Devon
Time to decision
165 weeks
Contracts for Difference
AR5
REPD reference
7451

The scheme also includes 35 MW of battery storage, recorded separately in REPD (operational).

Who decides

ApplicationsMid DevonUK
Decided applications (solar, wind, battery)3910,236
Refused13 (33%)19%
Solar refused11 of 3412%
Onshore wind refused1 of 145%
Battery storage refused1 of 416%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Winham Farmsolar farm5operational1.8
Paytherden Solar Farm (Peradon)solar farm49under construction2.9
Rutton Farm, Whimple - Horton Solar Farmsolar farm49.9approved, not built5.1
Little Toms Solar Farmsolar farm5under construction5.5
Exeter Substation, Broadclystbattery storage125approved, not built6.1
Stoneshill Farmsolar farm5operational6.2
Pithayessolar5refused6.6
Saundercroft Solar Farmsolar farm7operational6.8
National Grid Substationbattery storage100approved, not built6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8235, -3.3723).