Energy Projects Near You

Winham Farm (5 MW solar farm)

Winham Farm is a 5 MW solar farm project in Mid Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 December 2015; the record was last updated on 16 February 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
16 February 2016record last updated
Mid Devoncouncil area

Planning timeline

DateStage
7 April 2014Application submitted
4 July 2014Planning permission granted
1 November 2015Construction started
1 December 2015Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
16 February 2016
Operator or applicant
Hive Energy
Planning authority
Mid Devon
Planning application reference
14/00536/MFUL
Site area
11.1 ha
Address (REPD)
Land at NGR 301672 103703 (Land West of Winham Farm) Westcott
Council area (by location)
Mid Devon
Time to decision
13 weeks
REPD reference
2095

Earlier applications for this site

ApplicationMWSubmittedOutcome
Winham Farm 13/01408/MFUL514 November 2013withdrawn 20 January 2014

Who decides

ApplicationsMid DevonUK
Decided applications (solar, wind, battery)3910,236
Refused13 (33%)19%
Solar refused11 of 3412%
Onshore wind refused1 of 145%
Battery storage refused1 of 416%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Langford Solar Farmsolar farm35operational1.8
Paytherden Solar Farm (Peradon)solar farm49under construction4.5
Little Toms Solar Farmsolar farm5under construction4.6
Rutton Farm, Whimple - Horton Solar Farmsolar farm49.9approved, not built5.8
Exeter Substation, Broadclystbattery storage125approved, not built6.0
Stoneshill Farmsolar farm5operational6.0
National Grid Substationbattery storage100approved, not built6.4
Saundercroft Solar Farmsolar farm7operational6.6
Saundercroft Road, Broadclystbattery storage57approved, not built6.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8245, -3.3974).