Little Toms Solar Farm (5 MW)

Little Toms Solar Farm is a 5 MW solar farm project in Mid Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 June 2025; the record was last updated on 25 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
under constructionstatus in REPD
25 July 2025record last updated
Mid Devoncouncil area

Planning timeline

DateStage
28 November 2023Application submitted
20 June 2024Planning permission granted
1 June 2025Construction started

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
under construction
Record last updated
25 July 2025
Operator or applicant
PS Renewables
Planning authority
Mid Devon
Planning application reference
23/01838/MFUL
Site area
6.7 ha
Address (REPD)
North of Little Toms
Council area (by location)
Mid Devon
Time to decision
29 weeks
Name in REPD
Little Toms - Solar Farm
REPD reference
13014

Who decides

ApplicationsMid DevonUK
Decided applications (solar, wind, battery)3910,236
Refused13 (33%)19%
Solar refused11 of 3412%
Onshore wind refused1 of 145%
Battery storage refused1 of 416%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Stoneshill Farmsolar farm5operational2.8
Great Curham Farmsolar farm8refused3.3
Dean Hill Road Solar Farmsolar farm49.9approved, not built3.6
Winham Farmsolar farm5operational4.6
Langford Solar Farmsolar farm35operational5.5
Paytherden Solar Farm (Peradon)solar farm49under construction8.4
Broadpath Landfillsolar farm5abandoned8.5
Ayshford Court Farmsolar farm5operational9.1
Junction 27, Westleighbattery storage400approved, not built9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8635, -3.4172).