Dean Hill Road Solar Farm (49.9 MW)

Dean Hill Road Solar Farm is a 49.9 MW solar farm project in Mid Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 30 November 2023, not yet built; the record was last updated on 24 September 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
24 September 2024record last updated
Mid Devoncouncil area

Planning timeline

DateStage
4 January 2023Application submitted
30 November 2023Planning permission granted
30 November 2026Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
24 September 2024
Operator or applicant
Low Carbon Storage Ireland
Planning authority
Mid Devon
Planning application reference
22/02374/MFUL
Site area
60.4 ha
Address (REPD)
Dean Hill Road Willand, Cullompton
Council area (by location)
Mid Devon
Time to decision
47 weeks
Contracts for Difference
AR6
Name in REPD
Dean Hill Road - Solar Farm
REPD reference
11753

Who decides

ApplicationsMid DevonUK
Decided applications (solar, wind, battery)3910,236
Refused13 (33%)19%
Solar refused11 of 3412%
Onshore wind refused1 of 145%
Battery storage refused1 of 416%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Stoneshill Farmsolar farm5operational1.1
Great Curham Farmsolar farm8refused2.1
Little Toms Solar Farmsolar farm5under construction3.6
Broadpath Landfillsolar farm5abandoned4.9
Ayshford Court Farmsolar farm5operational5.6
Junction 27, Westleighbattery storage400approved, not built6.5
Winham Farmsolar farm5operational7.1
Langford Solar Farmsolar farm35operational7.2
Wiseburrow Farmsolar farm6refused on appeal9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8877, -3.3839).