Wiseburrow Farm (6 MW solar farm)

Wiseburrow Farm is a 6 MW solar farm project in Mid Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 9 June 2016; the record was last updated on 1 July 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWsolar farm
refused on appealstatus in REPD
1 July 2016record last updated
Mid Devoncouncil area

Planning timeline

DateStage
16 July 2015Application submitted
4 December 2015Refused by the planning authority
19 January 2016Appeal lodged
9 June 2016Appeal refused

Project details

Technology
solar farm
Capacity
6 MW
Status (REPD)
refused on appeal
Record last updated
1 July 2016
Operator or applicant
Sum Farming UK
Planning authority
Mid Devon
Planning application reference
15/01108/MFUL
Appeal reference
APP/Y1138/W/15/3141503
Site area
11.0 ha
Address (REPD)
Wiseburrow Farm, Greenham
Council area (by location)
Mid Devon
Time to decision
20 weeks
REPD reference
5940

Earlier applications for this site

ApplicationMWSubmittedOutcome
Wiseburrow Farm 14/01932/MFUL628 November 2014refused 12 February 2015

Who decides

ApplicationsMid DevonUK
Decided applications (solar, wind, battery)3910,236
Refused13 (33%)19%
Solar refused11 of 3412%
Onshore wind refused1 of 145%
Battery storage refused1 of 416%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Junction 27, Westleighbattery storage400approved, not built3.2
Ayshford Court Farmsolar farm5operational3.6
Broadpath Landfillsolar farm5abandoned4.6
Tonedale Farmsolar farm5operational5.2
Dean Hill Road Solar Farmsolar farm49.9approved, not built9.2
Great Curham Farmsolar farm8refused10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9566, -3.312).