Energy Projects Near You

Broadpath Landfill (5 MW solar farm)

Broadpath Landfill is a 5 MW solar farm project in Mid Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 30 January 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
abandonedstatus in REPD
30 January 2018record last updated
Mid Devoncouncil area

Planning timeline

DateStage
29 September 2015Application submitted
18 December 2015Planning permission granted
18 December 2018Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
abandoned
Record last updated
30 January 2018
Operator or applicant
Viridor
Planning authority
Mid Devon
Planning application reference
15/01511/MFUL
Site area
8.3 ha
Address (REPD)
Viridor Waste Management Ltd, Broad Path Landfill Site, Uffculme, Burlescombe, Cullompton
Council area (by location)
Mid Devon
Time to decision
11 weeks
REPD reference
5851

Who decides

ApplicationsMid DevonUK
Decided applications (solar, wind, battery)3910,236
Refused13 (33%)19%
Solar refused11 of 3412%
Onshore wind refused1 of 145%
Battery storage refused1 of 416%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Ayshford Court Farmsolar farm5operational1.9
Junction 27, Westleighbattery storage400approved, not built3.1
Wiseburrow Farmsolar farm6refused on appeal4.6
Dean Hill Road Solar Farmsolar farm49.9approved, not built4.9
Stoneshill Farmsolar farm5operational5.7
Great Curham Farmsolar farm8refused6.3
Little Toms Solar Farmsolar farm5under construction8.5
Tonedale Farmsolar farm5operational9.1
Dunkeswell Airfieldbattery storage6.5approved, not built9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9173, -3.3317).