Broadpath Landfill (5 MW solar farm)
Broadpath Landfill is a 5 MW solar farm project in Mid Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 30 January 2018.
5 MWsolar farm
abandonedstatus in REPD
30 January 2018record last updated
Mid Devoncouncil area
Planning timeline
| Date | Stage |
|---|---|
| 29 September 2015 | Application submitted |
| 18 December 2015 | Planning permission granted |
| 18 December 2018 | Permission expired |
Project details
- Technology
- solar farm
- Capacity
- 5 MW
- Status (REPD)
- abandoned
- Record last updated
- 30 January 2018
- Operator or applicant
- Viridor
- Planning authority
- Mid Devon
- Planning application reference
- 15/01511/MFUL
- Site area
- 8.3 ha
- Address (REPD)
- Viridor Waste Management Ltd, Broad Path Landfill Site, Uffculme, Burlescombe, Cullompton
- Council area (by location)
- Mid Devon
- Time to decision
- 11 weeks
- REPD reference
- 5851
Who decides
| Applications | Mid Devon | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 39 | 10,236 |
| Refused | 13 (33%) | 19% |
| Solar refused | 11 of 34 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Battery storage refused | 1 of 4 | 16% |
| Median time from submission to decision | 13.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 8 / 5 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Ayshford Court Farm | solar farm | 5 | operational | 1.9 |
| Junction 27, Westleigh | battery storage | 400 | approved, not built | 3.1 |
| Wiseburrow Farm | solar farm | 6 | refused on appeal | 4.6 |
| Dean Hill Road Solar Farm | solar farm | 49.9 | approved, not built | 4.9 |
| Stoneshill Farm | solar farm | 5 | operational | 5.7 |
| Great Curham Farm | solar farm | 8 | refused | 6.3 |
| Little Toms Solar Farm | solar farm | 5 | under construction | 8.5 |
| Tonedale Farm | solar farm | 5 | operational | 9.1 |
| Dunkeswell Airfield | battery storage | 6.5 | approved, not built | 9.4 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9173, -3.3317).