Energy Projects Near You

Ayshford Court Farm (5 MW solar farm)

Ayshford Court Farm is a 5 MW solar farm project in Mid Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 28 March 2013; the record was last updated on 14 June 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
14 June 2013record last updated
Mid Devoncouncil area

Planning timeline

DateStage
24 December 2010Application submitted
3 June 2011Planning permission granted
28 March 2013Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
14 June 2013
Operator or applicant
AEE Renewables
Planning authority
Mid Devon
Planning application reference
10/01930/MFUL
Site area
15.8 ha
Address (REPD)
Westleigh, Tiverton, Devon
Council area (by location)
Mid Devon
Time to decision
23 weeks
REPD reference
1569

Who decides

ApplicationsMid DevonUK
Decided applications (solar, wind, battery)3910,236
Refused13 (33%)19%
Solar refused11 of 3412%
Onshore wind refused1 of 145%
Battery storage refused1 of 416%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Junction 27, Westleighbattery storage400approved, not built1.2
Broadpath Landfillsolar farm5abandoned1.9
Wiseburrow Farmsolar farm6refused on appeal3.6
Dean Hill Road Solar Farmsolar farm49.9approved, not built5.6
Great Curham Farmsolar farm8refused6.4
Stoneshill Farmsolar farm5operational6.6
Tonedale Farmsolar farm5operational8.7
Little Toms Solar Farmsolar farm5under construction9.1
Buckhayes Farmsolar farm6refused9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9319, -3.3459).