Buckhayes Farm (6 MW solar farm)

Buckhayes Farm is a 6 MW solar farm project in Mid Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 21 August 2013; the record was last updated on 23 September 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWsolar farm
refusedstatus in REPD
23 September 2013record last updated
Mid Devoncouncil area

Planning timeline

DateStage
4 February 2013Application submitted
21 August 2013Refused by the planning authority

Project details

Technology
solar farm
Capacity
6 MW
Status (REPD)
refused
Record last updated
23 September 2013
Operator or applicant
Lumicity
Planning authority
Mid Devon
Planning application reference
13/00185/MFUL
Address (REPD)
Chevithorne,, Tiverton, Devon
Council area (by location)
Mid Devon
Time to decision
28 weeks
REPD reference
1742

Who decides

ApplicationsMid DevonUK
Decided applications (solar, wind, battery)3910,236
Refused13 (33%)19%
Solar refused11 of 3412%
Onshore wind refused1 of 145%
Battery storage refused1 of 416%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Keens Farmsolar farm5.1refused on appeal4.2
Gratton Copsesolar5application withdrawn4.5
West Holcombesolar farm5.5under construction5.1
West Holcombesolar farm5.5application withdrawn5.1
Junction 27, Westleighbattery storage400approved, not built8.7
Ayshford Court Farmsolar farm5operational9.6
Great Curham Farmsolar farm8refused9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9742, -3.465).