Keens Farm (5.1 MW solar farm)

Keens Farm is a 5.1 MW solar farm project in Mid Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 8 July 2014; the record was last updated on 5 August 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.1 MWsolar farm
refused on appealstatus in REPD
5 August 2014record last updated
Mid Devoncouncil area

Planning timeline

DateStage
7 November 2012Application submitted
6 February 2013Refused by the planning authority
8 July 2014Appeal refused

Project details

Technology
solar farm
Capacity
5.1 MW
Status (REPD)
refused on appeal
Record last updated
5 August 2014
Operator or applicant
juwi Renewable Energies
Planning authority
Mid Devon
Planning application reference
12/01522/MFUL
Appeal reference
13/00015/WR
Address (REPD)
Morebath, Tiverton, Devon
Council area (by location)
Mid Devon
Time to decision
13 weeks
REPD reference
1871

Who decides

ApplicationsMid DevonUK
Decided applications (solar, wind, battery)3910,236
Refused13 (33%)19%
Solar refused11 of 3412%
Onshore wind refused1 of 145%
Battery storage refused1 of 416%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Gratton Copsesolar5application withdrawn0.4
West Holcombesolar farm5.5under construction2.0
West Holcombesolar farm5.5application withdrawn2.0
Buckhayes Farmsolar farm6refused4.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.0113, -3.4737).