West Holcombe (5.5 MW solar farm, REPD 5255)

West Holcombe is a 5.5 MW solar farm project in Mid Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 August 2020; the record was last updated on 21 September 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.5 MWsolar farm
under constructionstatus in REPD
21 September 2020record last updated
Mid Devoncouncil area

Planning timeline

DateStage
28 August 2014Application submitted
20 January 2015Appeal lodged
24 June 2015Planning permission granted
24 June 2015Appeal allowed
1 August 2020Construction started

Project details

Technology
solar farm
Capacity
5.5 MW
Status (REPD)
under construction
Record last updated
21 September 2020
Operator or applicant
Wessex Solar Energy
Planning authority
Mid Devon
Planning application reference
14/01452/MFUL
Appeal reference
APP/Y1138/W/14/3001908
Address (REPD)
Land at NGR 299298 125070 (East Of Bowdens Lane) Shillingford Devon
Council area (by location)
Mid Devon
Time to decision
43 weeks
REPD reference
5255

Who decides

ApplicationsMid DevonUK
Decided applications (solar, wind, battery)3910,236
Refused13 (33%)19%
Solar refused11 of 3412%
Onshore wind refused1 of 145%
Battery storage refused1 of 416%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
West Holcombesolar farm5.5application withdrawn<0.1
Gratton Copsesolar5application withdrawn1.7
Keens Farmsolar farm5.1refused on appeal2.0
Buckhayes Farmsolar farm6refused5.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.0192, -3.4482).