Energy Projects Near You

National Grid Substation (100 MW battery storage)

National Grid Substation is a 100 MW battery storage project in East Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 22 August 2025, not yet built; the record was last updated on 10 September 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

100 MWbattery storage
approved, not builtstatus in REPD
10 September 2025record last updated
East Devoncouncil area

Planning timeline

DateStage
15 October 2024Application submitted
22 August 2025Planning permission granted
22 August 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
100 MW
Status (REPD)
approved, not built
Record last updated
10 September 2025
Operator or applicant
Penso Power (BW ESS)
Planning authority
East Devon
Planning application reference
25/0063/MFUL
Address (REPD)
E/O National Grid Substation, Broadclyst, Exeter
Council area (by location)
East Devon
Time to decision
44 weeks
Name in REPD
National Grid Substation - Battery Energy Storage System
REPD reference
17484

Who decides

ApplicationsEast DevonUK
Decided applications (solar, wind, battery)5510,236
Refused17 (31%)19%
Solar refused9 of 3612%
Battery storage refused8 of 1916%
Median time from submission to decision21.0 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Burrowton Farmsolar farm5operational0.9
Crannaford Solar Farmsolar farm12.5operational1.1
Saundercroft Solar Farmsolar farm7operational1.1
Saundercroft Farmbattery storage290approved, not built1.1
Saundercroft Road, Broadclystbattery storage57approved, not built1.1
Exeter Substation, Broadclystbattery storage125approved, not built1.3
Kerswell Barton Farm, Broadclystsolar farm16.2approved, not built3.1
Poltimore solar farmsolar farm5.5refused3.1
Pithayessolar5refused3.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7678, -3.4131).