Poltimore solar farm (5.5 MW)

Poltimore solar farm is a 5.5 MW solar farm project in East Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 19 December 2013; the record was last updated on 14 February 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.5 MWsolar farm
refusedstatus in REPD
14 February 2014record last updated
East Devoncouncil area

Planning timeline

DateStage
25 July 2013Application submitted
19 December 2013Refused by the planning authority

Project details

Technology
solar farm
Capacity
5.5 MW
Status (REPD)
refused
Record last updated
14 February 2014
Operator or applicant
INRG Solar
Planning authority
East Devon
Planning application reference
13/1650/MFUL
Site area
12.4 ha
Address (REPD)
Land To The East Of The M5 And West Of Jarvishayes Poltimore
Council area (by location)
East Devon
Time to decision
21 weeks
REPD reference
1427

Who decides

ApplicationsEast DevonUK
Decided applications (solar, wind, battery)5510,236
Refused17 (31%)19%
Solar refused9 of 3612%
Battery storage refused8 of 1916%
Median time from submission to decision21.0 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Kerswell Barton Farm, Broadclystsolar farm16.2approved, not built1.0
Burrowton Farmsolar farm5operational2.4
National Grid Substationbattery storage100approved, not built3.1
Crannaford Solar Farmsolar farm12.5operational3.6
Saundercroft Farmbattery storage290approved, not built4.0
Saundercroft Road, Broadclystbattery storage57approved, not built4.0
Saundercroft Solar Farmsolar farm7operational4.1
Exeter Substation, Broadclystbattery storage125approved, not built4.4
Pithayessolar5refused6.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7596, -3.4555).