Saundercroft Farm (290 MW battery storage)

Saundercroft Farm is a 290 MW battery storage project in East Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 12 January 2024, not yet built; the record was last updated on 2 February 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

290 MWbattery storage
approved, not builtstatus in REPD
2 February 2024record last updated
East Devoncouncil area

Planning timeline

DateStage
18 May 2023Application submitted
12 January 2024Planning permission granted
21 January 2029Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
290 MW
Status (REPD)
approved, not built
Record last updated
2 February 2024
Operator or applicant
Exeter Storage Limited (Statera Energy)
Planning authority
East Devon
Planning application reference
23/0962/MFUL
Address (REPD)
Saundercroft Farm, Whimple, Exeter
Council area (by location)
East Devon
Time to decision
34 weeks
Name in REPD
Saundercroft Farm - Battery Energy Storage System
REPD reference
13980

Who decides

ApplicationsEast DevonUK
Decided applications (solar, wind, battery)5510,236
Refused17 (31%)19%
Solar refused9 of 3612%
Battery storage refused8 of 1916%
Median time from submission to decision21.0 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Saundercroft Road, Broadclystbattery storage57approved, not built<0.1
Saundercroft Solar Farmsolar farm7operational0.1
Crannaford Solar Farmsolar farm12.5operational0.6
Exeter Substation, Broadclystbattery storage125approved, not built0.8
National Grid Substationbattery storage100approved, not built1.1
Burrowton Farmsolar farm5operational1.6
Pithayessolar5refused2.5
Rutton Farm, Whimple - Horton Solar Farmsolar farm49.9approved, not built3.2
Kerswell Barton Farm, Broadclystsolar farm16.2approved, not built3.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7641, -3.3988).