Solar, wind and battery projects near Exeter (EX3)
57 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of EX3 (Exeter): 6 are waiting for a planning decision, 32 approved but not yet running, 9 operational. The largest live scheme is Saundercroft Farm (290 MW battery storage, approved on 12 January 2024, not yet built), 9.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of EX3
Projects of 1 MW and more (29)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Winslade Parksolar farm | solar farm | 1.9 | approved, not builtupdated Mar 2025 | Jan 2024 | refused May 2024 | Mar 2025 | East Devon | 2.1 |
| Kenniford Farmsolar farm | solar farm | 4 | abandonedupdated Sep 2018 | Jan 2015 | granted Oct 2015 | Sep 2018 | East Devon | 2.2 |
| Orchard Parksolar farm | solar farm | 5.1 | refused on appealupdated Oct 2016 | Dec 2014 | refused Dec 2015 | Oct 2016 | East Devon | 2.5 |
| Higher Bagmore Farm, Ebford Lane -Battery Energy Storage Systembattery storage | battery storage | 50 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | East Devon | 3.2 |
| Westexe, Greendale Business Parkrooftop solar | rooftop solar | 1.1 | approved, not builtupdated Feb 2024 | Jan 2024 | granted Feb 2024 | Feb 2024 | East Devon | 4.7 |
| Exeter City Council Solar Panel Arraysolar farm | solar farm | 1.2 | approved, not built may be out of dateupdated Nov 2021 | Sep 2019 | granted Oct 2019 | Nov 2021 | Exeter | 5.0 |
| Council Green Waste Facilitybattery storage | battery storage | 1 | approved, not built may be out of dateupdated Dec 2021 | Sep 2019 | granted Oct 2019 | Dec 2021 | Exeter | 5.0 |
| Coombe Farmsolar farm | solar farm | 8 | operationalupdated Jun 2015 | May 2014 | granted Sep 2014 | Jun 2015 | East Devon | 5.6 |
| School Of Education, Heavitree Roadrooftop solar | rooftop solar | 1 | approved, not builtupdated May 2025 | Dec 2024 | granted Jan 2025 | May 2025 | Exeter | 5.7 |
| Blackhill Quarry, Woodburybattery storage | battery storage | 60 | approved, not built may be out of dateupdated Aug 2023 | Nov 2022 | granted Jul 2023 | Aug 2023 | East Devon | 6.5 |
| Bystock Solar Farmsolar farm | solar farm | 4.1 | operationalupdated May 2015 | Jul 2014 | granted Sep 2014 | May 2015 | East Devon | 7.0 |
| Kerswell Barton Farm, Broadclystsolar farm | solar farm | 16.2 | approved, not builtupdated Sep 2025 | Mar 2025 | granted Aug 2025 | Sep 2025 | East Devon | 7.3 |
| Bowhay Farmsolar farm | solar farm | 10.7 | application withdrawnupdated Aug 2017 | Oct 2012 | — | Aug 2017 | Teignbridge | 7.4 |
| Veiges Farm Solar Parksolar farm | solar farm | 5 | abandonedupdated Feb 2019 | Sep 2015 | granted Feb 2016 | Feb 2019 | East Devon | 7.6 |
| Higher Hawkerland Farm, Sidmouth Road Solar Farmsolar farm | solar farm | 18 | approved, not builtupdated Mar 2023 | Oct 2022 | granted Apr 2023 | Mar 2023 | East Devon | 7.7 |
| Poltimore solar farmsolar farm | solar farm | 5.5 | refusedupdated Feb 2014 | Jul 2013 | refused Dec 2013 | Feb 2014 | East Devon | 8.2 |
| Belle Vue Roadsolar farm | solar farm | 1.1 | approved, not built may be out of dateupdated Aug 2023 | Apr 2023 | granted Aug 2023 | Aug 2023 | Exeter | 8.5 |
| Liverton Farmsolar farm | solar farm | 4.8 | operationalupdated Mar 2015 | Oct 2013 | granted Jan 2014 | Mar 2015 | East Devon | 8.6 |
| Ford Oaks Solar & Green Infrastructure Facilitysolar farm | solar farm | 30 | under constructionupdated Feb 2026 | May 2022 | granted Nov 2023 | Feb 2026 | East Devon | 8.7 |
| Burrowton Farmsolar farm | solar farm | 5 | operationalupdated Jul 2018 | Apr 2011 | granted Oct 2011 | Jul 2018 | East Devon | 8.8 |
| St Francis Court Farmsolar farm | solar farm | 4 | operationalupdated Mar 2017 | Nov 2013 | granted May 2014 | Mar 2017 | East Devon | 9.0 |
| Crannaford Solar Farmsolar farm | solar farm | 12.5 | operationalupdated Aug 2014 | Feb 2013 | granted Sep 2013 | Aug 2014 | East Devon | 9.1 |
| Great Houndbeare Farmsolar farm | solar farm | 10 | operationalupdated Jul 2018 | Jul 2013 | granted Nov 2013 | Jul 2018 | East Devon | 9.2 |
| National Grid Substationbattery storage | battery storage | 100 | approved, not builtupdated Sep 2025 | Oct 2024 | granted Aug 2025 | Sep 2025 | East Devon | 9.7 |
| Saundercroft Farmbattery storage | battery storage | 290 | approved, not builtupdated Feb 2024 | May 2023 | granted Jan 2024 | Feb 2024 | East Devon | 9.7 |
| Saundercroft Road, Broadclystbattery storage | battery storage | 57 | approved, not builtupdated Aug 2025 | Jan 2025 | granted Jul 2025 | Aug 2025 | East Devon | 9.7 |
| Strete Farm Solar Farmsolar farm | solar farm | 4.8 | operationalupdated Apr 2013 | May 2012 | granted Aug 2012 | Apr 2013 | East Devon | 9.7 |
| Saundercroft Solar Farmsolar farm | solar farm | 7 | operationalupdated Jul 2018 | Oct 2012 | granted Jan 2013 | Jul 2018 | East Devon | 9.8 |
| Rockbeare Hillsolar farm | solar farm | 15 | approved, not built may be out of dateupdated Sep 2020 | Jan 2020 | granted Jul 2020 | Sep 2020 | East Devon | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (28)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Darts Farm Shopping Village, Clyst St Georgerooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Mar 2023 | Feb 2023 | granted Mar 2023 | Mar 2023 | East Devon | 0.8 |
| David Lloyd Leisure Club, Sandy Park Wayrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Oct 2023 | Jul 2023 | granted Sep 2023 | Oct 2023 | Exeter | 2.7 |
| William Pollard & Co, Oak Houserooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2022 | Aug 2022 | granted Sep 2022 | Nov 2022 | Exeter | 3.6 |
| The Vapormatic Companyrooftop solar | rooftop solar | 0.1 | approved, not builtupdated May 2023 | May 2023 | granted Jun 2023 | May 2023 | Exeter | 3.6 |
| Howmet, Kestrel Wayrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jan 2023 | Jul 2022 | granted Aug 2022 | Jan 2023 | Exeter | 3.7 |
| Matford Way, Matfordrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2023 | Oct 2022 | granted Nov 2022 | Jan 2023 | Exeter | 4.2 |
| Crealy Adventure Park, Clyst St Marysolar farm | solar farm | 0.9 | approved, not built may be out of dateupdated Oct 2022 | Aug 2022 | granted Sep 2022 | Oct 2022 | East Devon | 4.2 |
| Hill Barton Business Park, Clyst St Marybattery storage | battery storage | 0.2 | application submitted may be out of dateupdated Jul 2024 | Jun 2024 | — | Jul 2024 | East Devon | 4.2 |
| Bittern Road Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Oct 2024 | Jul 2024 | granted Oct 2024 | Oct 2024 | Exeter | 4.5 |
| Emperor House, Grenadier Road Solar Panels & Car Park Replacementsolar farm | solar farm | 0.5 | approved, not builtupdated Sep 2025 | Dec 2023 | granted Aug 2025 | Sep 2025 | Exeter | 5.0 |
| Electricity Sub Station, Babbage Way - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | application withdrawnupdated Sep 2024 | Jun 2024 | — | Sep 2024 | East Devon | 5.0 |
| Greendale Business Park, Woodbury Salterton Battery Farmbattery storage | battery storage | — | refusedupdated Jun 2025 | Jan 2025 | refused May 2025 | Jun 2025 | East Devon | 5.1 |
| Blackhorse Lane - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Oct 2024 | Aug 2024 | granted Oct 2024 | Oct 2024 | East Devon | 5.2 |
| Electricity Sub Station, Tithebarn Waybattery storage | battery storage | 0.2 | approved, not builtupdated Dec 2024 | May 2024 | granted Oct 2024 | Dec 2024 | Exeter | 5.3 |
| Blackhorse Lane, Clyst Honiton Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Dec 2024 | Jul 2024 | granted Oct 2024 | Dec 2024 | Exeter | 5.4 |
| Sainsburys Supermarket, Hill Barton Roadrooftop solar | rooftop solar | 0.6 | application submitted | Jun 2026 | — | — | Exeter | 5.4 |
| Pinhoe Road - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Mar 2025 | Dec 2024 | granted Feb 2025 | Mar 2025 | Exeter | 5.6 |
| Wares Farm, Clyst Honiton - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Oct 2024 | Jul 2024 | granted Oct 2024 | Oct 2024 | East Devon | 6.0 |
| Skypark, Spitfire Avenuerooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jun 2026 | Mar 2026 | granted May 2026 | Jun 2026 | East Devon | 6.0 |
| Morrison Supermarket, Prince Charles Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2023 | Oct 2022 | granted Nov 2022 | Jan 2023 | Exeter | 6.1 |
| Exteter Airport, London Road - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Feb 2025 | Dec 2024 | granted Feb 2025 | Feb 2025 | East Devon | 6.4 |
| Car Park Guildhall Shopping Centre, Queen Streetrooftop solar | rooftop solar | 0.3 | application submittedupdated Feb 2026 | Jan 2026 | — | Feb 2026 | Exeter | 6.7 |
| Streatham Campus, Stocker Roadrooftop solar | rooftop solar | — | refusedupdated May 2023 | Feb 2023 | refused Apr 2023 | May 2023 | Exeter | 7.6 |
| Lower Veiges Plantationbattery storage | battery storage | — | abandonedupdated Feb 2019 | Dec 2015 | — | Feb 2019 | East Devon | 7.6 |
| Holland Hall, Clydesdale Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2025 | Apr 2025 | granted Jun 2025 | Jun 2025 | Exeter | 8.0 |
| Bradham Lane - Micro Energy Storagebattery storage | battery storage | 0.2 | application withdrawnupdated Apr 2026 | Jan 2026 | — | Apr 2026 | East Devon | 8.4 |
| Langdon Hospital, Langdonsolar farm | solar farm | — | application submittedupdated Dec 2025 | Nov 2025 | — | Dec 2025 | Teignbridge | 9.6 |
| Langdon Hospital, Langdonbattery storage | battery storage | — | application submittedupdated Dec 2025 | Nov 2025 | — | Dec 2025 | Teignbridge | 9.6 |
Distance from the average position of the EX3 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 24 | 1 | 9 | 9 | 2 | 84.8 |
| Rooftop solar | 14 | 2 | 11 | 0 | 1 | 5.6 |
| Battery storage | 19 | 3 | 12 | 0 | 1 | 560 |
MW in pipeline: pending, approved and under-construction capacity.
How Exeter decides solar, wind and battery applications
| Applications | Exeter | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 17 | 10,236 |
| Refused | 1 (6%) | 19% |
| Solar refused | 1 of 13 | 12% |
| Battery storage refused | 0 of 4 | 16% |
| Median time from submission to decision | 8.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 1 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near EX3, 8 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.